From: Daphne Wallace
To: Jeffrey Epstein <jeevacation@gmail.com>
Cc: ann rodriquez
Subject: Photos - September 5, 2015
Date: Fri, 04 Sep 2015 21:04:27 +0000
Attachments: MBR_flooring_(1).JPG; MBR_flooring_(2).JPG; MBR_flooring_(3).JPG;
MBR flooring_(4).JPG; MBR_flooring_(5).JPG; Pebble_Beach_cleanup_(1).JPG;
Pebble_Beach cleanup_(2).JPG; Pebble_Beach_cleanup_(3).JPG;
Pebble_Beach_cleanup_(4).JPG; Pebble_Beach_cleanup_(5).JPG;
Pebble Beach cleanup_(6).JPG; Pebble_Beach_cleanup_(7).JPG;
Pebble Beach cleanup_(8).JPG; Pebble_Beach_cleanup_(9).JPG;
Pebble Beach cleanup_(10).JPG; Pebble_Beach_cleanup_(11).JPG;
Pebble Beach cleanup_(12).JPG; Pebble_Beach_cleanup_(13).JPG;
Pebble_Beach_cleanup_(14).JPG; Pebble_Beach_cleanup_(15).JPG;
Pebble Beach cleanup_(16).JPG; Cabana_l_Grohe_shower_fixtures_(1).JPG;
Caban;_l_Grate_shower_fixtures_(2).JPG; Cabana_1_Grohe_shower_fixtures_(3).JPG;
Cabana_l_Grohe_shower_fixtures_(4).JPG; Cabana_1_Grohe_shower_fixtures_(5).JPG;
Cabana_l_Grohe_shower_fixtures_(6).JPG; Cabana_1_Grohe_shower_fixtures_(7).JPG;
Cabana_l_Grohe_shower_fixtures_(8).JPG; Cabana_2_Grohe_shower_fixtures_(1).JPG;
Cabana_2_Grohe_shower_fixtures_(2).JPG; Cabana_2_Grohe_shower_fixtures_(3).JPG;
Cabana_4_Bath door_repaired_(1).JPG; Cabana_4_Bath_door_repaired_(2).JPG;
Cabana_4 Bath__door_repaired_(3).JPG;
New_Ectr;_firm_matteressfor_Cabana_4_bed.JPG; Dining_Terrace_wall_cleaned.JPG;
Kitchen_cabinet_doors_no_longer_rub_(1).JPG;
Kitchen_cabinet_doors_no_longer_rub_(2).JPG;
Wirettmder_Kitchen_table_straightened_out_(1).JPG;
Wires_under_Kitchen_table_straightened_out_(2).JPG;
Info_Center roof repainted_(1).JPG; Info_Center_roof_repainted_(2).JPG;
Palm transplanted_at_New_Waterfall_(1).JPG;
Palm transplanted_at_New_Waterfall_(2).JPG;
Palm transplanted_at_New_Waterfall_(3).JPG;
Palm transplanted_at_New_Waterfall_(4).JPG; New_rocking_chairs.JPG
Greetings Sir,
September 5 photos for your review and comments:
MBR flooring - Pokey will work on Sunday - he is unable to come tomorrow
Pebble Beach cleanup - in progress - Jules says will be completed by next Friday 9/11
Cabana 1 Grohe shower fixtures - installation almost competed - Danny E has to shorten the neck on the pipe
where the water comes out of the wall and into the handheld fixture
Cabana 2 Grohe shower fixtures - the valve cartridge on one of the fixtures is missing - the company is trying to
locate a replacement and Anna will also try to find the part here on STT
Cabana 4 bathroom door - repaired and rehung
Cabana 4 bed - Anna purchased the new extra firm mattress - it is in place
EFTA00647903
Dining Terrace wall - a clogged spouting was the cause of the water backing up and dripping down the wall - the
spouting was cleared, but the spouting going into the downspout will need to be widened - the wall was cleaned,
and will be repainted
Kitchen cabinet doors - the hinges were changed so the doors no longer drag and rub together
Kitchen wiring - Jermaine tidied up the wires running under the kitchen table
Info Center roof - repainted today
Palm at Waterfall bench - the palm transplanted
New rocking chairs - purchased to replace chairs on the St. John terrace, MBR bath terrace and Blue beach deck
Landscaping - no progress photos today - all of the crew were focused on island wide cleanup in case you arrive
over the weekend
Punch-lists - we are finalizing the start and completion dates to try to give you correct information
Respectfully submitted, Daphne
EFTA00647904
AI Analysis
Summarize this document or ask questions about its contents using Claude.
Typical cost: less than $0.01 per query with Haiku. Model can be changed in Settings.
From: Daphne Wallace
To: Jeffrey Epstein <jeevacation@gmail.com>
Cc: ann rodriquez
Subject: Photos - September 5, 2015
Date: Fri, 04 Sep 2015 21:04:27 +0000
Attachments: MBR_flooring_(1).JPG; MBR_flooring_(2).JPG; MBR_flooring_(3).JPG;
MBR flooring_(4).JPG; MBR_flooring_(5).JPG; Pebble_Beach_cleanup_(1).JPG;
Pebble_Beach cleanup_(2).JPG; Pebble_Beach_cleanup_(3).JPG;
Pebble_Beach_cleanup_(4).JPG; Pebble_Beach_cleanup_(5).JPG;
Pebble Beach cleanup_(6).JPG; Pebble_Beach_cleanup_(7).JPG;
Pebble Beach cleanup_(8).JPG; Pebble_Beach_cleanup_(9).JPG;
Pebble Beach cleanup_(10).JPG; Pebble_Beach_cleanup_(11).JPG;
Pebble Beach cleanup_(12).JPG; Pebble_Beach_cleanup_(13).JPG;
Pebble_Beach_cleanup_(14).JPG; Pebble_Beach_cleanup_(15).JPG;
Pebble Beach cleanup_(16).JPG; Cabana_l_Grohe_shower_fixtures_(1).JPG;
Caban;_l_Grate_shower_fixtures_(2).JPG; Cabana_1_Grohe_shower_fixtures_(3).JPG;
Cabana_l_Grohe_shower_fixtures_(4).JPG; Cabana_1_Grohe_shower_fixtures_(5).JPG;
Cabana_l_Grohe_shower_fixtures_(6).JPG; Cabana_1_Grohe_shower_fixtures_(7).JPG;
Cabana_l_Grohe_shower_fixtures_(8).JPG; Cabana_2_Grohe_shower_fixtures_(1).JPG;
Cabana_2_Grohe_shower_fixtures_(2).JPG; Cabana_2_Grohe_shower_fixtures_(3).JPG;
Cabana_4_Bath door_repaired_(1).JPG; Cabana_4_Bath_door_repaired_(2).JPG;
Cabana_4 Bath__door_repaired_(3).JPG;
New_Ectr;_firm_matteressfor_Cabana_4_bed.JPG; Dining_Terrace_wall_cleaned.JPG;
Kitchen_cabinet_doors_no_longer_rub_(1).JPG;
Kitchen_cabinet_doors_no_longer_rub_(2).JPG;
Wirettmder_Kitchen_table_straightened_out_(1).JPG;
Wires_under_Kitchen_table_straightened_out_(2).JPG;
Info_Center roof repainted_(1).JPG; Info_Center_roof_repainted_(2).JPG;
Palm transplanted_at_New_Waterfall_(1).JPG;
Palm transplanted_at_New_Waterfall_(2).JPG;
Palm transplanted_at_New_Waterfall_(3).JPG;
Palm transplanted_at_New_Waterfall_(4).JPG; New_rocking_chairs.JPG
Greetings Sir,
September 5 photos for your review and comments:
MBR flooring - Pokey will work on Sunday - he is unable to come tomorrow
Pebble Beach cleanup - in progress - Jules says will be completed by next Friday 9/11
Cabana 1 Grohe shower fixtures - installation almost competed - Danny E has to shorten the neck on the pipe
where the water comes out of the wall and into the handheld fixture
Cabana 2 Grohe shower fixtures - the valve cartridge on one of the fixtures is missing - the company is trying to
locate a replacement and Anna will also try to find the part here on STT
Cabana 4 bathroom door - repaired and rehung
Cabana 4 bed - Anna purchased the new extra firm mattress - it is in place
EFTA00647903
Dining Terrace wall - a clogged spouting was the cause of the water backing up and dripping down the wall - the
spouting was cleared, but the spouting going into the downspout will need to be widened - the wall was cleaned,
and will be repainted
Kitchen cabinet doors - the hinges were changed so the doors no longer drag and rub together
Kitchen wiring - Jermaine tidied up the wires running under the kitchen table
Info Center roof - repainted today
Palm at Waterfall bench - the palm transplanted
New rocking chairs - purchased to replace chairs on the St. John terrace, MBR bath terrace and Blue beach deck
Landscaping - no progress photos today - all of the crew were focused on island wide cleanup in case you arrive
over the weekend
Punch-lists - we are finalizing the start and completion dates to try to give you correct information
Respectfully submitted, Daphne