From: emad hanna
To: "Gary Kerney"
Cc: Jeffrey Epstein <jeevacation®gmail.com>
Subject: Re:
Date: Mon, 16 May 2011 21:26:38 +0000
Gary,
Other items that I have not seen you respond to are (unless you responded to JE and did not include me on the e
mail)
Ion Schedule
Dock House
More People
Tile Layer
Nursery Floor
Mowing
Fire Fuel Desalination Mechanical done by 4/17
Thank you
Emad Hamm
Project Controller
HBRK Associates
301 East 66th St
Suite 10F
New York, NY 10065
Cell
LSJ Office
St. Thomas
NY Office
Fax
On May 16, 2011, at 2:38 PM, Gary Kemey wrote:
schedule for the 4th
Main pool
the building slab will be poured and block going up
the pool equipment will be installed and water in pool
the retaining walls around cottage will be up
the deck will be concrete,ready to lay tile(tile comes after the building is stoned)
still on target for 10/3
Flag pole pool
EFTA00878552
the building will be framed in and plastering underway
the pool equipment will be in and water in the pool (assumes we get tile selection)
the deck will be concrete(tile happens after shelter and plaster)
walls will be underway
still on target for 9/15