From: Kyle reavis •
To: "jeffrey E." <jeevacation@grnail.com>
Subject: Fwd: Jeffers
Date: Mon, 14 Jan 2019 18:46:59 +0000
Mr Epstein,
Mr Jeffers has pushed back the start of the roads, and told me his contract is not finalized. He needs two weeks
from the time his contract is executed to gather his men and materials. I have set up a meeting 1 week out to
cover logistics and operations.
Kyle
Forwarded message
From: Kyle reavis
Date: Mon, Jan 14, 2019 at 1:04 PM
Subject: Re: Jeffers
To: Richard Kahn
Cc: Daphne Wallace
Rich,
I just spoke to Jeffers and he said the contract is not finalized yet, and that it is with you. He said once that is
done then he will need two weeks once that is finalized. I told him to contact me 1 week out for an onsite
logistics meeting. Is this true or is he blowing smoke?
Kyle
On Mon, Jan 14, 2019 at 8:10 AM Richard Kahn > wrote:
why would I be calling him when logistics and staging is next step
kyle you asked for advice last week and you need to start anticipating things as opposed to reacting...
perfect example is steel buildings
you sent out for 3 quotes mid december and they all said 3 weeks..
mr epstein should not have to ask this morning where quotes are before you reach out to vendors...
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York, NY 10022
to
fax
cell
EFTA01008541
On Jan 14, 2019, at 7:01 AM, Kyle reavis <1 > wrote:
Rich,
I havent heard anything from Jeffers, is he still planning on starting this week? I can call him in a bit if you
are busy. Thank you.
Kyle