From: Stephanie Remington >
To: J <jeevacationggmail.com>
Subject: Re: Progress Report (01/28/19 - 02/03/19)
Date: Mon, 04 Feb 2019 12:22:26 +0000
Thank you, Sir.
On Mon, Feb 4, 2019 at 8:08 AM J <jeevacation@gmail.com> wrote:
well done
On Mon, Feb 4, 2019 at 6:36 AM Stephanie Remington < > wrote:
Correction: Mr Jeffers, not Mr Eli, to begin this week.
On Mon, Feb 4, 2019 at 5:00 AM Stephanie Remington < > wrote:
Please note:
This is a summary of the week's focus, not a comprehension of all projects.
All Divisions. Finish cleaning out all division work spaces.
Carpentry. - Complete install of LSJ tiki ceiling. Install FP Pool Temporary Countertop. Replace
coral stone by Chillax Bath. Repair Cabana 4 from a/c repairs. Replacement of collapsed
retaining wall at LSJ nursery near completion. Hinge replacements and rust removal. New bath
mirrors installed — required sink faucet removed in chillax, lights taken down and put back up in
all and tile adjustment for one.
Electrical. LSJ Tiki lights in. FP Pool awning adjusted. New speakers in theater room installed.
Replaced pool pump and lighting. Remove faucet for mirror install — Chillax bath for mirror
install. Permanent electric to LSJ dock. Repaired leak in storage room below Cabana 2. Lights
removed-beach.
Engineering. Pressure wash karts, rock crusher, car mixer. Clean back rooms of wreck shop.
Change attachment on lull JLG. Continue work on ambulance. Parts order w/Daphne. Repair
water tank. Assist w/barge runs (water truck to GSJ, etc.), haul away old mule, batteries, locate
tech-ambulance. Assist w/removal — light generators from beach.
Heavy Equipment. Lay and set GSJ septic. Apron work of dock to protect intake pipe.
Reinstated boat ramp (ready for Elderfield). Grated LSJ roads. Dug holes for turpentines.
Assisted in transplanting. Four done.
Housekeeping. In additional to usual rounds - GSJ and LSJ, assist with spraying, sweeping
walkways. Staff cottage and Sam's. Take down Theater room for speaker install, clean and put
room back.
Landscaping. Worked with Boschulte overall landscaping, improvements. Moved four
turpentines. String Lights down from MC Palms. Carried off scrap wood — nursery wall. Stone
lining along roads. Clean road grates.
Marine. Nautica back from BVI. Tubes close to finished for Sportis. Nanna is only boat stored on
GSJ, goes into the water this week in prep for principal arrival. Ferry service is down for
maintenance next week. Barge will do morning and afternoon crew runs until further notice.
Possible New York trip for new barge lead.
EFTA01028905
Painters. Painted walls and epoxied floors — Painting and Carpentry divisions. Continued paint
splatter removal at MC. Painted patched area in Cabana 4. Painted storage room and floor —
Cabana 2. Pool grates painted and installed.
RO/Maintenance. Work w/Gemini. Flush system. Routine maintenance, pools.
Contractors on island this past week:
Boschulte - landscaping
Reefco — repairs and maintenance
Gemini - RO
EB - GSJ
Grand Design - Countertops
Danny - MC Pool Wall (capped top of wall — MC, making strong progress)
Many thanks to all for all the hard work.
Other Notes:
• No Work or Workers on GSJ Monday (02/04) — Wednesday (02/06) per principal
• Cabinet top for FP Pool damaged by heavy equipment while relocating from cabanas
to FPPool area; project stalled, need clarification if we will move forward w this
company or find someone else.
• Received Premium and Diesel fuel
• Trash removal on both islands
• Mr. Eli and co. to begin concrete road projects in coming week.
• GSJ septic in place — ready for JPK.
• Copying other division/project leads so can add information I might have missed.
• Please note new work cell number:
Stephanie Remington
LSJE, LLC
Stephanie Remington
LSJE, LLC
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation0i;gmail.com and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved