Construction Proposal
August 7, 2O15
By the Contractor: Betteroads Asphalt Corporation
For the Project: LSJ_Added Aggregate Base
Little St. James Island
VI
SCOPE OF WORK:
Place and compact 3 inches aggregates base as per plan
TOTAL BASE PRICE: $90,712.00
Project Totals:
Name Quantity Unit Cost Unit Total Cost
Aggregate
Crushed stone Aggregate Base 1360 530.00 Ton 540.800.00
Materials Transport
Trucking and Hauling 68 $400.00 Each $27.200.00
Excavation and Fill
Loading and/or Spreading Base 1360 $3.00 Ton 54.080AX)
Structural Compaction 1360 $5.00 Ton S6.800.00
Company Overhead
Company Overhead Percentage 15.00% I $0.00 Percent of Costs SI 1.832.00
Grand Total $90,712.00
Page 1 of 2
L.1.1Added Aggregate Proposal
EFTA00608342