From:
To: jeevacation@gmail.com
CC:
Subject: Gil update
Date: Fri, 18 Mar 2011 15:11:55 +0000
just
Gentlemen,
The right gear is completed and will be shipped today. We should receive this by Monday.
The left gear is in the machine shop, they have performed an NDT of the effected area and it appears there is enough
material to remove the corrosion and remain within limits. They will proceed this weekend with the machining and check the
remaining thickness again on Monday and get engineering involved for approval as well. There is still a good chance the
corrosion is beyond acceptable limits. I should have an answer no later that Tuesday on this gear leg.
Everything else is just about wrapped up.
If you have any further questions, please feel free to contact me.
Have a great weekend!
Best Regards
Jet Aviation St. Louis, Inc.
Joe Allen
Gulfstream Customer Support Manager
an update from Midcoast:
EFTA00655264