From: Craig Martin
To: jeffrey epstein <jeevacation@gmail.com>
Subject: Re:
Date: Fri, 27 Apr 2012 13:01:53 +0000
ok
From: jeffrey epstein <ieevacatio mail.com>
To: Craig Marlin
Sent: Friday, April 27, 2012 1:18 AM
Subject: Re:
Need breakdown of equipment
Sent from my iPad
On Apr 26, 2012, at 9:57 PM, Craig Martin < > wrote:
Michael Glidden called back this afternoon.
His quote to run electric from the gym to 5 palms was:
$21,140 for labor
S11,740 for material, his material includes transformer, disconnects, breaker boxes, etc, everything except
conduit and cable,
$32,880 total
LSJ to provide:
Cable, Conduit, Trenching, manhole Structures,
based on 1500 ft ( Michael wants to verify again)
4/0 cable is 3.84 per ft
Ground cable is .78 ft
conduit is 11.99 per 10 ft section ( not per ft as we had thought last nite)
$8325.50 cost for LSJ on the low end. Brice had suggested we run two extra conduits for future use. That
would add to cost.
So basic package is $41,205.50 plus LSJ labor and material. Need to verify length and if LSJ wants two
extra conduits.
I can send this to Tom in the AM to get LSJ labor figures.
Hope this helps.
Craig
From: Jeffrey Epstein <'eevacation mail.com>
To: Craig Martin <
Sent: Thursday, April 26, 2012 7:28 PM
Subject:
I need the jauquin proposal and the glidden numne to merely run wire to five plams from the gym.
EFTA00660140
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation@gmail.com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA00660141