schedule for the 4th
Main pool
the building slab will be poured and block going up
the pool equipment will be installed and water in pool
the retaining walls around cottage will be up
the deck will be concrete,ready to lay tile(tile comes after the building is stoned)
still on target for 10/3
Flag pole pool
the building will be framed in and plastering underway
the pool equipment will be in and water in the pool (assumes we get tile selection)
the deck will be concrete(tile happens after shelter and plaster)
walls will be underway
still on target for 9/15