#2 cabana gutted 8 +- months ago
On 6/9/09 9:22 AM, "curtis" wrote:
• April 4th - CZM permit start up was required— exterior demolition and plant clearing, silt fencing.
• April 27th — 28th Master Bathroom taken apart — during inventory of Bedroom/Bathroom
• Sinks outside for no good reason — but they are undamaged and will be properly stored.
• We can begin - Master bath foundation, walls, electrical and plumbing roughing when you give us the go ahead,
Building Permit received last week.
• Exterior column design unclear.
• Details & specifications based on exactly what you had before — we can complete most issues with this
information — No Designer on Board.
• We can reused — Vanities which are in fine shape — shower doors to speed schedule forward -
• Need budget approval to allocate funds — order long lead
On 6/9/09 8:05 AM, "JEE" <jeevacation@gmail.com> wrote:
when was my master bathrroom taken apart„ why are the sinks outside for weeks on end ? when was the cabana
taken down„ when is the master bath project actually going to begin„