American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
system or subsystem exceeding $10
million unless certain conditions were
Keyeite Yellow Flag - Negative Treatment
Distinguished by Gengler v. U.S. ex rel. its Dept. of Defense and met, and (2) Department's failure to
Navy. E.D.Cal.. August 24.2006 comply with statute's requirements did
F.3d 1368 not render contract void ab initio.
United States Court of Appeals,
Federal Circuit. Questions answered and case
remanded.
AMERICAN TELEPHONE
AND TELEGRAPH COMPANY, Rader, Circuit Judge, concurred in the
and result and filed opinion in which Mayer,
Lucent Technologies Inc., Chief Judge, and Lourie, Circuit Judge,
Plaintiffs—Appellants, joined.
v.
UNITED STATES, Plager, Circuit Judge, dissented in part,
Defendant/Cross—Appellant. concurred in part, and filed opinion.
Nos. 95- 5153, 95- 5154.
Opinion, 124 F.3d 1471, vacated.
May 26, 1999.
Synopsis West Headnotes (5)
Contractor sued Government under
Contract Disputes Act for recovery
Ill Public Contracts
of expenditures under research and
development contract. The Court of • Compensation
Federal Claims, John P. Wiese, J., 32 United States
Fed.CI. 672, ruled that contract was • Compensation
void and that quantum meruit relief Navy contract for
was available, but certified questions development of ship-towed.
for interlocutory appeal. The Court undersea surveillance system
of Appeals originally affirmed, but, was for "major system or
on rehearing en banc, the Court subsystem," for purposes
of Appeals, Pauline Newman, Circuit of statute prohibiting
Judge, held that: (1) Navy contracts for Department of Defense from
development of ship-towed, undersea entering into fixed price
surveillance system was for "major contracts for development of
system or subsystem," for purposes major system or subsystem
of statute prohibiting Department of exceeding $10 million unless
Defense from entering into fixed price certain conditions were
contracts for development of major met, notwithstanding either
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 1
EFTA00797875
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
agency's reliance on separate ab initio, as statute itself
statute to define major system did not announce sanction
as having $75 million floor of contract invalidity, and
or fact that contract was contract had been fully
funded over multiple years. performed. Act December 22,
10 U.S.C.A. § 2302(5); Act 1987, § 101(b), Sec. 8118, 101
December 22, 1987, § 101(b), Stat. 1329.
Sec. 8118, 101 Stat. 1329.
24 Cases that cite this
9 Cases that cite this headnote headnote
121 Administrative Law and 141 Public Contracts
Procedure offr. Unauthorized or Illegal
e- Erroneous or Contracts
unreasonable construction; United States
conflict with statute o- Unauthorized or Illegal
Although an agency's Contracts
interpretation of a statute Invalidation of government
it administers is indeed contract is not a necessary
entitled to deference, agency consequence when a statute
discretion does not extend or regulation has been
to changing a clearly stated contravened, but must be
dollar figure. considered in light of
the statutory or regulatory
Cases that cite this headnote purpose, with recognition
of the strong policy of
131 Public Contracts supporting the integrity of
1— Compensation contracts made by and with
United States the United States.
Compensation
13 Cases that cite this
Failure of Department headnote
of Defense to comply
with statute setting forth
internal review and reporting 151 Contracts
requirements for fixed price o- Nature and Essentials in
contract for development of General
major system or subsystem The invalidation of a contract
exceeding $10 million did not after it has been fully
render such contract void performed is not favored.
WESTLAW 2019 Thomson Reuters. No claim to original U.S. Government Works. 2
EFTA00797876
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
amicus curiae Federal Circuit Bar
11 Cases that cite this Association. With him on the brief was
headnote Clarence T. Kipps, Jr. Of counsel on the
brief were L. James D'Agostino, Reed
Smith Shaw & McClay, of McLean,
Virginia; and George Hutchinson,
Attorneys and Law Firms Executive Director, Federal Circuit Bar
Association, of Washington, DC.
*1369 C. Stanley Dees, McKenna &
Cueno, L.L.P., of Washington, DC, Before MAYER, Chief Judge,
argued for plaintiffs-appellants. With NEWMAN, PLAGER, LOURIE,
him on the brief was J. Keith Burt. Of CLEVENGER, RADER, SCHALL,
counsel on the brief were Thomas R. BRYSON, and GAJARSA, Circuit
Suher, and Dean L. Grayson, Lucent Judges. *
Technologies, Inc., of Washington,
DC. Opinion
Bryant G. Snee, Assistant Director,
Commercial Litigation Branch, Civil Opinion for the court filed by Circuit
Division, Department of Justice, Judge NEWMAN, in which Circuit
of Washington, DC, argued for Judges CLEVENGER, SCHALL,
defendant-cross appellants. With him BRYSON, and GAJARSA join.
on the brief was David M. Cohen, Opinion concurring in result filed by
Director. Of counsel on the brief were Circuit Judge RADER, in which Chief
Robert D. Hogue, James H. Haag, Judge MAYER and Circuit Judge
Attorneys, Office of General Counsel, LOURIE join. Opinion dissenting-in-
Department of the Navy, of Arlington, part and concurring-in-part filed by
Virginia. Circuit Judge PLAGER.
Caryl A. Potter, III, Sonnenschein NEWMAN, Circuit Judge.
Nath & Rosenthal, of Washington, DC,
We took this appeal and cross-appeal
for amicus curiae Electronic Industries
en banc to reconsider the questions
Alliance and Aerospace Industries
of law presented, upon certification
Association of America, Inc. With him
for interlocutory appeal, concerning
on the brief were Elizabeth A. Ferrell,
the applicability of § 8118 of the
of Washington, DC; Alan M. Posner,
Defense Appropriations Act of 1987 to
of Chicago, Illinois; and Roger K.
a contract between the Department of
Heidenreich, of St. Louis, Missouri.
the Navy and the American Telephone
John Lloyd Rice, Miller & Chevalier, and Telegraph Company. The Court of
Chartered, of Washington, DC, for Federal Claims ruled that in view of the
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 3
EFTA00797877
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
failure of the Department of Defense to Diameter Array. The contract was
comply with § 8118, the contract, which a "Total Package Procurement,"
had been performed, was void ab initio. requiring design of shipboard and
We now hold that the contract was shore-based electronics, ship-winch
not void, and remand to the Court of interface and tow cable, and an
Federal Claims for further proceedings acoustic and electronic array some
in accordance with this premise. 8,000 feet long, to meet the new Soviet
submarine capabilities. The contract
required research, development, and
The Reduced Diameter Array Contract the delivery and testing of an
This contract arose in Cold War engineering development model, at
response to the new ultra-quiet a fixed ceiling price of $19,221,630,
Soviet submarines, which were and included an option to the
difficult to monitor using available Navy to acquire a second engineering
technology and equipment. Effective development model at a fixed ceiling
antisubmarine response requires that price of $3,510,253, and an additional
hostile submarines be reliably detected, option to acquire three production-
classified, located, and tracked. The level models at a fixed ceiling price of
Navy, among its programs for this $8,475,466.
purpose, employed an integrated
undersea acoustic sonar system called The contract was successfully
the Surveillance Towed—Array Sensor performed by AT & T over a period of
System (SURTASS). In SURTASS a five years. With the price adjustments
suitably equipped surface vessel tows an to which the Navy agreed during
array of undersea detection equipment performance, the final fixed price
through the ocean, while the equipment was approximately $34.5 million. AT
collects and transmits appropriate data & T states that technical problems
for processing on shipboard and for and unknowns arose throughout
transmission to shore-based facilities. performance, and that its total cost was
The President's Annual Report *1370 at least $91 million. The Navy rejected
to the Congress for fiscal 1987, on AT & T's requests for restructuring the
the topic of Antisubmarine Warfare contract and other relief, although AT
Forces, referred to SURTASS as & T directed attention to § 8118 of
"[o]ne of our most important ongoing the Defense Appropriations Act and
programs in this area." Id. at 188. relevant Department of Defense policy
directives concerning procurement of
On December 31, 1987, after research and development for new
competitive bidding, the Navy awarded technologies.
AT & T a fixed price incentive
fee contract for a subsystem of
SURTASS, referred to as the Reduced
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 4
EFTA00797878
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
AT & T duly brought suit in the pursuant to unjust enrichment
Court of Federal Claims under the principles.
Contract Disputes Act. On cross
motions for summary judgment the A panel of the Federal Circuit, by split
issues arising from the enactment of decision, affirmed the ruling that the
§ 8118 were presented and argued. contract was void ab initio. The court
The Court of Federal Claims ruled also held that no relief was available
that § 8118 applied to this contract, to AT & T on any theory, except
that it had not been complied with perhaps to replevin the goods that had
by the Department of Defense, and been delivered to the Navy. Upon the
that the contract consequently was void petitions of both sides we have reheard
ab initio. Responding to AT & T's the matter en banc. I
proposal that the appropriate remedy
was to reform the contract into the
cost-reimbursement form favored by Section 8118 ofthe Defense
§ 8118, the Court of Federal Claims Appropriations Act of1987
held that since there had never been a Concern about the use of fixed price
valid contract it could not be reformed. contracts for research and development
The court held, however, that AT & *1371 phases pervades defense
T was entitled to compensation for procurement. In 1971 Department of
its work on the basis of quantum Defense Directive (DODD) 5000.1
meruit, on a theory of implied-in- stated that "[i]t is not possible to
fact contract. Before proceeding to determine the precise production cost
determine quantum, the court certified of a new complex defense system
for interlocutory appeal, in accordance before it is developed," and established
with 28 U.S.C. § 1292(d)(2), the the policy of using cost-reimbursement
following questions: price terms for procurement of research
and development. The Directive
(i) whether a contract executed in stated: "Fixed price contracts are
violation of statutory restrictions on normally not appropriate for research
the obligation and expenditure of and development phases." DODD
appropriated funds may be declared 5000.1 & D.9.g (as amended, Sept.
void from the start at the instance of 1, 1987). The Federal Acquisitions
the performing contractor, and, if so, Regulations governing R & D
contracts also embodied this policy.
(ii) whether compensation for See, e.g., 48 C.F.R. § 35.006(c)
benefits conferred upon the (1984-1998) ("Because the absence of
Government (pursuant to the voided precise specifications and difficulties
contract) can be predicated on an in estimating costs with accuracy
implied-in-fact contract with the (resulting in a lack of confidence in cost
amount of recovery to be determined estimates) normally precludes using
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 5
EFTA00797879
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
fixed-price contracting for R & D, the the cost-reimbursement type contract.
use of cost-reimbursement contracts is Id. at 11.
usually appropriate.")
At ensuing hearings on the 1988
The record states that in the 1980s, Defense budget, concern was expressed
despite these policy directives, the Navy about the continuing use of fixed
returned to fixed price contracting price contracts for high-cost, high-
for R & D as part of the risk development projects, as well
Total Package Procurement concept. as concern for meeting congressional
This in turn led to congressional oversight and allocation obligations
investigations and hearings. An under this form of procurement.
investigation conducted by the House Department of Defense Appropriations
Appropriations Committee concluded for 1988: Hearings Before the
that for the development phases Defense Subcomm. of the Comm. on
of new technologies, the Navy's Appropriations, 100th Cong., 454-
use of fixed price contracting 55 (1987). Legislatively implementing
resulted in program delays, cost these concerns, the House included in
overruns, contractor claims, non- the Defense Appropriations Act of 1987
participation, and litigation. See the provision that became § 8118:
Surveys & Investigations Staff, Report
to the Comm. on Appropriations, U.S. § 8118. None of the funds provided
House of Representatives: Navy Fixed for the Department of Defense in this
Price Contracting in the Research, Act may be obligated or expended for
Development, Test and Evaluation fixed price-type contracts in excess of
(RDT & E) Account, 100th Cong., $10,000,000 for the development of
1st Sess. (1987). The Report stated a major system or subsystem unless
that: "Although Navy officials at the Under Secretary of Defense for
the headquarters level have predicted Acquisition determines, in writing,
immense success for the acquisition that program risk has been reduced
policy, the opinions expressed by Navy to the extent that realistic pricing
and other Service field procurement can occur, and that the contract type
officials and technical experts indicated permits an equitable and sensible
that [fixed price contracting] generally allocation of program risk between
[has] proved unsuitable in an R the contracting parties: Provided,
& D environment." Id. at ii. The That the Under Secretary may
Report concluded that the nature not delegate this authority to any
of the work in research and persons who hold a position in the
exploratory development contracting Office of the Secretary of Defense
"most frequently necessitates" use of below the level of Assistant Under
Secretary of Defense: Provided
further, That the Under Secretary
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 6
EFTA00797880
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
report to the Committees on Department, and required quarterly
Appropriations of the Senate and reports of such awards to the House and
House of Representatives in writing, Senate Appropriations Committees.
on a quarterly basis, *1372 the The government argues first that '8118
contracts which have obligated did not apply to the Reduced Diameter
funds under such a fixed price-type Array contract, thus eliminating any
developmental contract. need for the Navy to have complied
with the statute. The Court of Federal
Pub.L. No. 100-202, § 8118, 101 Claims correctly held otherwise.
Stat. 1329, 1329-84 (Dec. 22, 1987).
The accompanying Conference Report Section 8118 by its terms applies to
reiterated congressional concern that "fixed price-type contracts in excess
the risks of failure and of cost of $10,000,000 for the development of
uncertainties be allocated equitably a major system or subsystem." The
between government and contractor, government argues that the Reduced
and stressed the desire to "maintain Diameter Array is not a "major
the government's credibility as a system," referring to a memorandum
reliable business partner." H.R. Conf. issued six weeks after enactment of §
Rep. No. 100-498 at 623 (Dec. 22, 8118 wherein the Under Secretary of
1987). Congress referred to the burden Defense defined "major system" for the
of a fixed price contract on the purposes of § 8118 as a system having
contractor when the miscalculation of a contract cost of over $75,000,000. In
development cost may have been that a Memorandum for Service Acquisition
of the government agency as well as Executives, Directors of the Defense
the contractor, and to the reluctance Agencies issued February 11, 1988,
of some highly qualified firms to enter Under Secretary of Defense for
into such contracts. The Conference Acquisition Costello instructed that
Report was unambiguous: "Fixed price "[t]he definition of major system at 10
contracts are normally not appropriate U.S.C. § 2302(5) is the definition of
for research and development phases." that term for the purpose of [§ 8118]."
Id. at 624. Thus Congress acted to This content was incorporated into
adjust the risks of developing the SECNAV Instruction 4210.6A (April
advanced technologies needed in the 13, 1988).
service of national defense.
121 Section 2302(5) is a provision
of chapter 137 of Subtitle A—
Application of Section 8118
General Military Law, which as then
[lj Section 8118 prohibited the award
written defined "major system" as a
of certain fixed price-type contracts
system costing more than $75,000,000
unless the program risk was evaluated
at a high level within the Defense
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
EFTA00797881
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
for research, development, test, and Inc., 467 U.S. 837, 842-43, 104 S.Ct.
evaluation: 2778, 81 L.Ed.2d 694 (1984) ("if the
intent of Congress is clear, that is the
10 U.S.C. § 2302(5). The term "major end of the matter").
system" means a combination of
elements that will function together In addition, the AT & T contract
to produce the capabilities required itself, and the Space and Naval
to fulfill a mission need. The elements Warfare Systems Command's guide
may include hardware, equipment, to the SURTASS, described the
software or any combination thereof, Reduced Diameter Array as a
but excludes construction or other "subsystem." Subsystems were not
improvements to real property. A defined in § 2305(5) and were not
system shall be considered a major mentioned in the Memorandum of the
system if (A) the Department of Under Secretary. However, subsystems
Defense is responsible for the costing more than $10,000,000 were
system and the total expenditures explicitly included in § 8118. Although
for research, development, test, the government now argues that the
and evaluation for the system Under Secretary's Memorandum and
are estimated to be more than SECNAV Instr. 4210.6A really covered
$75,000,000 (based on fiscal year a major system or a subsystem of
1980 constant dollars) or the eventual a major system, this interpretation is
total expenditure for procurement of contrary to the plain text of these
more than $300,000,000 (based on documents. It is apparent that the
fiscal year 1980 constant dollars).... Memorandum was contrary to the
statute, and in all events that it did not
The government argues that the agency
include subsystems such as the Reduced
had discretion to define the § 8118
Diameter Array.
"major system" in accordance with
'2302(5), and thereby to place a
The government also argues that not
$75,000,000 floor on the systems to
all of the funds expended under
which § 8118 would apply. However, it
the Reduced Diameter Array contract
was not within the agency's discretion
were appropriated in the corresponding
to rewrite § 8118 to replace the statutory
Appropriations Act, and thus that
threshold of $10,000,000 with that
the § 8118 prohibition on obligating
of $75,000,000. Although an agency's
or expending funds does not apply.
*1373 interpretation of a statute
Indeed, the contract was structured
it administers is indeed entitled to
for multi-year incremental funding.
deference, agency discretion does not
However, it is undisputed that the
extend to changing a clearly stated
starting research and development
dollar figure. See Chevron, U.S.A., Inc.
effort drew on several millions of
v. Natural Resources Defense Council,
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 8
EFTA00797882
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
dollars of appropriated funds. The the Senate and House Appropriations
multi-year funding does not excuse the Committees. Although the government
Defense Department from compliance stresses that the contract was awarded
with § 8118. only nine days after the enactment of §
8118, this does not excuse the failure of
Moreover, contrary to the all compliance.
government's argument, which is made
but not strongly pressed, this case does
not involve a funding deficiency or Consequences ofAgency
implicate the Anti—Deficiency Act, 31 Noncompliance With § 8118
U.S.C. § 1341. See Hercules Inc. v. PI We turn to the certified question
United States, 516 U.S. 417, 427, 116 of the consequences of this failure
S.Ct. 981, 134 L.Ed.2d 47 (1996) ("The of compliance by the Department of
Anti-Deficiency Act bars a federal Defense. AT & T states that § 8118
employee or agency from entering into was enacted at least in part for its
a contract for future payment of money protection, and that the agency, by
in advance of, or in excess of, an failing to obey the law, can not deprive
existing appropriation."); see generally AT & T of the protection of the
Ferris v. United States, 27 Ct.CI. law. AT & T argues that § 8118
542, 546 (1892) ("An appropriation is a "mandatory statute" restricting
per se merely imposes limitations the agency's authority to obligate and
upon the Government's own agents ... expend funds, and that the Navy's
its insufficiency does not pay the direct contravention of § 8118 rendered
Government's debts, nor cancel its the Reduced Diameter Array contract
obligations, nor defeat the rights of void ab initio.
other parties.") There is no issue in this
case of lack of appropriated funds. The government responds that
Congress chose and intended to enforce
We affirm the determination of the § 8118 *1374 through its oversight
Court of Federal Claims that § powers, and that AT & T can not
8118 applies to this contract. The benefit from whatever lapses may
government does not dispute that have occurred within the Department
the requirements of § 8118 were not of Defense in its compliance with
met by the Department of Defense. congressional oversight legislation. The
There is no assertion that the Under government stresses that § 8118 did not
Secretary of Defense for Acquisitions provide that these fixed price contracts
made or had made the program risk were prohibited, but only that the
and pricing determinations required Defense Department must review the
by § 8118, and no report of this risk and its allocation at a specified
contract is stated to have been made to executive level, and must report to
Congress on a quarterly basis.
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 9
EFTA00797883
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
history"). Congress simply tightened
14] Legislative intent and precedent the reporting provision, by moving
both lead to the conclusion that the from after-the-fact quarterly reports
AT & T contract was not void ab to before-award reports. Indeed, the
initio as a consequence of the agency's House version of § 8118 had initially
noncompliance. Invalidation of the required before-award reports, but
contract is not a necessary consequence this was dropped in Conference in
when a statute or regulation has been favor of the Senate version "to
contravened, but must be considered reduce the appearance of congressional
in light of the statutory or regulatory micromanagement." H.R. Conf. Rep.
purpose, with recognition of the strong No. 100-498 at 623 (Dec. 22, 1987).
policy of supporting the integrity of
contracts made by and with the United The Conference Report stated that if
States. In United States v. Mississippi Defense Department policy did not
Valley Generating Co., 364 U.S. 520, become more uniform, "more severe
81 S.Ct. 294, 5 L.Ed.2d 268 (1961) the restrictions" would be imposed. Id. This
Court explained that when a statute remark carries no hint of, and indeed
"does not specifically provide for the belies, an interpretation that § 8118 was
invalidation of contracts which are intended, upon enactment, to invalidate
made in violation of [its provisions]" any contract made without meeting
the court shall inquire "whether its internal review and reporting
the sanction of nonenforcement is requirements, for such a "restriction"
consistent with and essential to would already be extremely "severe."
effectuating the public policy embodied The statutory shift to before-award
in [the statute]." Id. at 563, 81 reports in succeeding years would be a
S.Ct. 294. Thus the policy underlying trivial discipline indeed, if meanwhile
the enactment must be considered all of the fixed price contracts within the
in determining the remedy for its statutory scope, although in the process
violation, when the statute itself does of performance, or as in this case fully
not announce the sanction of contract performed, were void ab initio.
invalidity.
Only a few months after enactment
The policy embodied in § 8118 of § 8118 the House Appropriations
is elucidated in the congressional Committee reported that the
response when § 8118 did not receive "enforcement of existing policy in this
full compliance from the Department of area has not yet been demonstrated,"
Defense. See Alabama Rural Fire Ins. H.R.Rep. No. 100-681 at 147 (June 10,
Co. v. United States, 215 Ct.C1. 442, 572 1988), and recommended a pre-award
F.2d 727, 733 (1978) ("illegality may reporting requirement (which was
be proved with reference to legislative included in the enactment for the next
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 10
EFTA00797884
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
fiscal year). The Senate Armed Services negate any reasonable inference that
Committee, considering this renewal, Congress intended simply to render
stated explicitly that noncompliance void ab initio, even after full
was not intended to be "the basis for performance, any fixed price contract
litigating the propriety of an otherwise for which the Under Secretary's review
valid contract": of risk allocation and the report to
the Committees were omitted. Congress
The committee recognizes that there can not have intended to charge
are circumstances in which fixed- the contracting partner with adverse
price development contracts are consequences depending on whether
appropriate (e.g., when costs and the Defense Department carried out the
foreseeable program risks can be internal responsibilities and filed the
reasonably anticipated), and the reports that Congress required.
committee expects the Department to
establish clear guidelines under this Nor is it the judicial role to
section for use of such contracts. discipline the agency's noncompliance
with the supervisory and reporting
*1375 It is the intent of the
instructions of congressional oversight.
committee that this section be
See Longshore v. United States,
applied in a manner that best serves
77 F.3d 440, 443 (Fed.Cir.1996)
the government's interests in the long
("Congress has undoubted capacity to
term health of the defense industry,
oversee the performance of Executive
and that this section not be used as
Branch agencies, consistent with its
the basisfor litigating the propriety of
constitutional authority. It is not for
an otherwise valid contract. Nothing
this court to instruct Congress on how
in this section shall be construed
to oversee and manage its creations.");
to affect the requirements of section
E. Walters & Co. v. United States, 217
8118 of the Department of Defense
Ct.CI. 254, 576 F.2d 362, 367 (1978)
Appropriations Act, 1988.
("The fact that a procurement practice
(Emphasis added.) S.Rep. No. 100- is prohibited does not necessarily mean
326, 100th Cong., 2d Sess. at 105 that it is therefore actionable. The
(May 4, 1988). This explicit statement discipline to be administered in such
of intent weighs heavily against cases is a responsibility of the cognizant
judicial invalidation of "an otherwise procurement officials within the agency
valid contract," for the clearly stated [and not] by this court"); cf. National
congressional purpose is contrary. Treasury Employees Union v. Campbell,
654 F.2d 784, 794 (D.C.Cir.1981)
These congressional responses, made (by statutory requirement that the
with knowledge of the agency's Comptroller General report on certain
imperfect compliance with § 8118, expenditures "Congress itself is in a
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 11
EFTA00797885
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
position to monitor and enforce its Schoenbrod v. United States, 187 Ct.CI.
spending limitations. It is not for 627, 410 F.2d 400, 403-04 (1969). We
us to question the effectiveness of take incidental note that the case at
existing remedies and infer additional bar also involved a disappointed bidder
remedies.") raising post-award objections, *1376
and that none of the objections were
Both the DoD administration of § based on § 8118.
8118, and the congressional response
to this administration, make clear In Harbor Gateway Commercial
that Congress did not intend that Property Owners' Ass'n v. United States
this enactment would terminate fully Environmental Protection Agency, 167
performed contracts because of this F.3d 602 (D.C.Cir.1999), a case stressed
flawed compliance. in the dissenting opinion hereto, the
court voided an EPA action because the
151 Precedent reinforces our conclusion Governor had not signed the request
that the Reduced Diameter Array as the statute required. However,
contract is not void ab initio. The there was no issue of performance,
invalidation of a contract after it has or reliance, or any other contractual
been fully performed is not favored. element. It is not before us to decide
Precedent shows that those contracts whether either party to the Reduced
that have been nullified, based on a Diameter Array contract could have
failure to meet a statutory or regulatory voided the contract early in its life
requirement, are contracts that have and without penalty; the contract was
not been substantially performed. E.g., performed for over five years, with no
Alabama Rural Fire Ins. Co. v. United record suggestion from either party that
States, 215 Ct.CI. 442, 572 F.2d 727, because of § 8118 there was no contract.
733-34 (1978). In Prestex, Inc. v.
United States, 162 Ct.CI. 620, 320 F.2d Judicial reluctance to annul performed
367, 374-75 (1963), the court held a contracts when the government did not
contract invalid, and refused to allow comply with a statutory or regulatory
any recovery because no performance requirement was explained by the Court
had occurred. It is not surprising that of Claims in John Reiner & Co. v.
much of the litigation raising issues of United States, 163 Ct.CI. 381, 325 F.2d
violation of statute or regulation at the 438, 440 (1963), stating that "the court
inception of government contracts has should ordinarily impose the binding
arisen in the bid protest context, where stamp of nullity only when the illegality
the asserted illegality has been explored is plain." In Reiner the court recognized
before substantial performance has the "dilemma" of a contractor who
occurred. E.g., CACI, Inc. v. Stone, becomes aware, while deep in the
990 F.2d 1233, 1235 (Fed.Cir.1993); performance of a contract, of a possible
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 12
EFTA00797886
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
procurement illegality he did not cause: (1978) the court sustained a contract
the contractor must either continue that was awarded after the contracting
to perform a contract of uncertain officer had negligently failed to meet
validity, or discontinue performance a regulatory responsibility; the court
and risk severe penalties if a court later held that the non-compliance with
disagrees with his assessment of the regulation was "a matter for internal
illegality. resolution" and "did not render the
resultant contract a nullity." In Clark
When a contract or a provision v. United States, 95 U.S. 539, 542, 24
thereof is in violation of law but L.Ed. 518 (1877) the Court held a parol
has been fully performed, the courts contract void for violation of the statute
have variously sustained the contract, of frauds, but allowed recovery on an
reformed it to correct the illegal implied contract theory.
term, or allowed recovery under an
implied contract theory; the courts The entirety of precedent strongly
have not, however, simply declared the supports our conclusion that the
contract void ab initio. For example, Reduced Diameter Array contract
in LaBarge Products v. West, 46 is not void ab initio. Precedent
F.3d 1547, 1552-53 (Fed.Cir.1995) does not favor the invalidation,
there was an illegal disclosure by based on governmental noncompliance
the government during bidding; this with internal review and reporting
court noted that the contract had procedures, of a contract that has been
been substantially performed and held fully performed by either contracting
that a valid contract existed despite party. 2
the violation. In Beta Systems, Inc. v.
United States, 838 F.2d 1179, 1185- *1377 Although the parties discuss
86 (Fed.Cir.1988) the court allowed possible remedies, the issue of what
reformation of the contract price term relief may be available to AT & T
to correct a regulatory violation, stating is not before us, for the Court of
that "[t]he risk of unintentional failure Federal Claims did not consider AT
of a contract term to comply with a & T's claims on the premise that the
legal requirement does not fall solely underlying contract was not void. We
on the contractor." In Urban Data have not considered this issue, and
Systems, Inc. v. United States, 699 F.2d express no view thereon.
1147, 1154 (Fed.Cir.1983) the court
held that a contract price term that
was contrary to law did not invalidate Answers to the Certified Questions
the fully performed contract. In Trilon For the reasons we have discussed, we
Educational Corp. v. United States, conclude that the agency's failure to
217 Ct.C1. 266, 578 F.2d 1356, 1360 comply with the obligations of § 8118
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 13
EFTA00797887
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
did not render the Reduced Diameter price-type contracts in
Array contract void ab initio. Any excess of $10,000,000
failure by the Department of Defense in for the development
its internal compliance with § 8118 can of a major system or
not be invoked, particularly after full subsystem....
contract performance, either to strip the
Navy of authority to have entered into
the contract or to bar AT & T from (emphasis added). This particular
presenting such claims, if any, that it section of the U.S.Code does not
may have. supply a definition of "major system."
However, § 2302(5) of title 10 of
The second certified question relates to the United States Code, which relates
remedy, but is based on the premise that to government procurement contracts
the contract was void ab initio. Since generally, defines "major system:"
that premise is incorrect, we do not
reach the second certified question.
The term "major
system" means a
Costs combination of
Each party shall bear its costs. elements that will
function together
QUESTIONS ANSWERED; CASE to produce the
REMANDED. capabilities required
to fulfill a mission
need.... A system
RADER, Circuit Judge, concurring in
shall be considered a
the result, in which MAYER, Chief major system if (A)
Judge, and LOURIE, Circuit Judge, the Department of
join.
Defense is responsible
Because § 8118 of the Defense for the system and the
Appropriations Act does not apply to total expenditures for
this contract, I concur. Section 8118 research,
provides in relevant part: development, test and
evaluation for the
system are estimated
None of the to be more than
funds provided for
$75,000,000 ... or
the Department of
(C) the system is
Defense in this Act
designated a "major
may be obligated or
system" by the head of
expended for fixed-
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 14
EFTA00797888
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
the agency responsible "major system," namely, designation
for the system. by the head of the agency. Thus,
a project beneath the $75,000,000
threshold of 10 U.S.C. § 2302(5) could
Therefore, the term "major system" nonetheless qualify as a "major system"
refers to systems either with estimated upon designation by the head of the
costs above $75,000,000 or systems agency.
"designated a `major system' by the
head of the agency responsible for the This court's opinion discounts
system." See 10 U.S.C. § 2302(5) (1986). the reasonable reconciliations of
Shortly after enactment of § 8118, the $10,000,000 contract amount
both the Department of Defense and requirement with the "major system"
the Navy incorporated this statutory classification requirement. Under the
definition into their interpretation of agency's reasonable interpretation,
that section. As the agency charged with the $10,000,000 contract amount
interpretation and application of the requirement serves as a floor for
statute, the Department of Defense's invoking § 8118 in contracts involving
reasonable interpretation of § 8118 a project designated as a "major
deserves deference. See Chevron U.S.A., system" by the department head.
Inc. v. Natural Resources Defense Furthermore, the $10,000,000 contract
Council, Inc., 467 U.S. 837, 844, 104 amount requirement does not lose
S.Ct. 2778, 81 L.Ed.2d 694 (1984). its meaning for systems whose
estimated costs exceed $75,000,000.
The Department of Defense and Navy's Development of a major system
interpretation alone gives meaning typically requires multiple contracts
to all of the words in the statute. with multiple developers. In these cases,
Both the Court *1378 of Federal the $10,000,000 requirement serves as a
Claims' interpretation and this court's floor for application of § 8118 to each
interpretation in this opinion would contract involved in the development
render the "major system or subsystem" of that "major system." Similarly, the
language superfluous and would invoke $10,000,000 trigger amount excludes
§ 8118 for any fixed-price contract from § 8118 any subsystem contracts
in excess of $10,000,000. This court within a major system which do not
chooses that course on the reasoning satisfy this threshold amount. For these
that the agency's interpretation "rewrite reasons, the $10,000,000 threshold
[s] § 8118 to replace the statutory continues to govern in conjunction
threshold of $10,000,000 with that of with the $75,000,000 threshold for a
$75,000,000." This reasoning, however, "major system." In sum, these dual
discounts the statute's alternative thresholds work together and provide a
method of categorizing a project as a reasonable explanation for the agency's
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 15
EFTA00797889
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
interpretation of these statutes. Because is a "subsystem" of a "major system."
reasonable, the agency's interpretation Although AT & T asserted below
deserves deference. that the Reduced Diameter Array
subsystem was a part of SURTASS,
Even without deference to the and that SURTASS was a major system
Departments of Defense and Navy, according to the requirements of 10
their proposed interpretation of § 8118 U.S.C. § 2302(5), by consent of the
alone gives meaning to all the statute's parties before the Court of Federal
terms and should therefore govern this Claims, that issue is not a subject of
court's resolution. As noted above, this the certified appeal. For these reasons, I
is the only interpretation which supplies would not apply § 8118 to the Reduced
meaning to all of the terms of the Diameter Array contract at issue in this
statute. Specifically, this is the only appeal.
interpretation which gives meaning
to the term "major system" as well
as the $10,000,000 contract amount
PLAGER, Circuit Judge, dissenting-in-
requirement.
part and concurring-in-part.
I must respectfully dissent. The
Finally, I read the term "subsystem" in
court refuses to honor an explicit
§ 8118 as linked to "major system" by
mandate of an *1379 unequivocal
its context within the statute. Although
Congressional enactment. "Legislative
neither 10 U.S.C. § 2302(5), nor the
interpretations of § 8118 proffered history" cannot justify that refusal.'
by the Department of the Defense A court has a responsibility to arrive
or the Navy address the definition at the right result in a case; it also
of "subsystem," the statute itself ties has the obligation to explain itself in a
the definition of this term to the manner that does no harm to the fabric
term "major system." In essence, this of the law. Though the right result may
interpretation would apply § 8118 eventually emerge, the route the court
to "major systems and subsystems takes to get there has the potential
of major systems." This reading for causing considerable harm to legal
preserves the statute's "major system principles that I deem important.
or subsystem" requirement rather than
expanding application of § 8118 to In the first part of its opinion, the court
all fixed-price-type contracts exceeding describes the Government's efforts over
$10,000,000. time to adjust the risks that are inherent
in cutting-edge R & D contracts so that
Furthermore, to my eyes, this appeal they are fair both to the Government
does not present the question of and the contractor. See slip op. at 1369-
whether this Reduced Diameter Array 70. These efforts begin at least in 1971
with DODD 5000.1, and culminate,
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 16
EFTA00797890
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
for purposes of this case, with the as a matter of law such contracts
enactment in 1987 of § 8118 as part were prohibited, and since there could
of that year's Department of Defense be no consideration offered for the
("DoD") Appropriations Act. See id. at contractor's promised performance.
1370-72. As the court explains, § 8118 Remarkably, the court reaches exactly
prohibited using Government funds for the opposite conclusion, and finds
fixed price-type R & D contracts except the contract valid, and presumably
under certain conditions. enforceable. For the reasons I shall
explain, I cannot join the court in this.
The court then sets out the history of the
R & D contract at issue in this case, and
concludes, correctly, that Section 8118
1.
applies to this DoD fixed price-type
alleged contract. See id. at 1372-73. The Omitting the inapplicable exception
court concludes, again correctly, that language and its related provisos,
the exception provided in the statute, the operative words of the statute
permitting a fixed price-type R & D are clear and to the point: "None
contract under certain conditions, is not of the funds provided for the PoDI
applicable since the DoD did not take in this [Appropriations' Act may be
the steps necessary to qualify for an obligated or expended for fixed price-
exception. See id. type contracts...." It is a rule of
constitutional law that, in absence of
This is the same conclusion on the an express appropriation, agencies may
point reached by the Court of Federal not spend, and a fortiori cannot validly
Claims, which this court now affirms. contract to spend, any federal dollars.
The court rejects the Government's See U.S. Const. art. I, § 9, cl. 7
various arguments to the contrary, and ("No Money shall be drawn from
finally concludes this part of its analysis the Treasury, but in Consequence of
with the statement that: "Although the Appropriations made by Law."). The
government stresses that the contract Supreme Court earlier reversed us when
was awarded only nine days after the in another context we failed to properly
enactment of § 8118, this does not apply that principle. See Office of
excuse the failure of all compliance." Id Personnel Management v. Richmond,
496 U.S. 414, 110 S.Ct. 2465, 110
Given that the court recognizes the L.Ed.2d 387 (1990).
language of the Act to expressly
prohibit the use of Government funds Here, we do not have simply an
for such a contract, the obvious and omission of authorization to expend;
ineluctable conclusion would appear to we have an outright prohibition:
be that there was no contract, since "None of the funds *1380 [otherwise
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 17
EFTA00797891
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
appropriated] may be expended ..." for Envtl. Protection Agency, 167 F.3d 602,
the precise purpose for which the DoD 607 (D.C.Cir.1999). 4
contracted. Surely it should not be
necessary for Congress to have added: In response to the Government's
"and we mean it," or perhaps, "and we argument that EPA officials considered
mean it, and if you try, it won't be any themselves to be in compliance, and
good, so don't even bother." in any event an invalidation of the
action would require that the action
It is not uncommon for Congress to be done again and would just cost the
put prohibitions such as that contained Government more money, the District
in § 8118 in Acts appropriating funds of Columbia Circuit answered:
to executive branch agencies.' A
recent case in point: Congress, in an
Appropriations Act which included We refuse to ignore
the U.S. Environmental Protection the plain language
Agency, 3 specified that "none of of the Act in order
the funds made available under to avoid potential
this heading may be used by the costs which would
Environmental Protection Agency ... not have arisen
[for certain described activities affecting had EPA complied
states] unless the Administrator with the statute's
receives a written request ... from the language in the first
Governor of the State...." The EPA, instance. Indeed, when
on the basis of an authorizing letter a statute's meaning
from a state official, not the Governor, is clear, and the
undertook such activity with regard to enactment is within
certain property in California. Affected the constitutional
interests appealed. authority of Congress,
the "sole function of
Judge Sentelle, writing for the Court of the courts is to enforce
Appeals for the District of Columbia it according to its
Circuit, found that the state official's terms."
letter did not meet the terms of the
statute, and readily concluded that,
in the absence of a letter from the Id. at 606 (emphasis added). That seems
Governor himself, the EPA action was to be the law on the subject; I know of
"null and void," and "was necessarily no cases to the contrary, and the court
invalid." Harbor Gateway Commercial here cites none.
Property Owners' Ass'n v. United States
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 18
EFTA00797892
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
In this case, AT & T, after due Government could neither offer or
negotiation with the Navy, offered pay consideration; no consideration, no
to make and sell to the Navy for contract, end of discussion, at least with
an agreed fixed price a submarine- respect to contract validity under basic
detecting piece of equipment. The Navy contract principles.
accepted the offer, and proposed to pay
for the work using funds from the 1987
Appropriations Act that contained the
2.
express prohibition set out above. As
the Harbor Gateway court explained, I cannot agree with the court that
the Navy's action was "null and void," the "purpose" of the statute overrides
and "necessarily invalid." its express terms. The court tells us
that this statute "must be considered
Furthermore, the Navy's action in in light of the statutory or regulatory
this case was taken for the purpose purpose, with recognition of the strong
of entering into a contract. But policy of supporting the integrity of
the Navy was legally incapable of contracts made by and with the United
using Government funds unless it told States." Slip op. at 1374. Clearly,
Congress what it was up to in the however, the purpose of this statute,
manner required by the statute, which expressed in no uncertain language, is
the Navy chose not to do. (It is exactly the opposite-it is intended to
difficult *1381 not to believe that prevent contracts with the United States
both parties were fully aware of the in contravention of its terms, not to
statute and simply chose to ignore support them.
it, though that is of no moment
to the issue before us. 5 ) Thus, It has been some years since a
not only was the act of contracting court-invented "purpose" so blatantly
prohibited by statute, but as a matter repealed a Congressional enactment.
of basic contract law no legally- Last century, in Rector, etc. of Holy
binding contract could be created: Trinity Church v. United States, 143
offer, acceptance, and consideration U.S. 457, 471, 12 S.Ct. 511, 36
remain a fundamental requirement for L.Ed. 226 (1892), the Supreme Court
a legally-binding contract, whether announced that this is a "Christian
between private parties or between a nation," and on that basis concluded
private party and the Government. that the purpose of a statute that
See, e.g., Harbert/Lummus Agrifuels banned immigration of foreign workers
Projects v. United States, 142 F.3d could not possibly be to prevent
1429, 1434 (Fed.Cir.1998); Trauma an English clergyman from coming
Serv. Group v. United States, 104 F.3d to work in the United States. In
1321, 1325 (Fed.Cir.1997). Here, the this century, and certainly in recent
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 19
EFTA00797893
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
times, purpose-inventing by judges has 501, 65 S.Ct. 335, 89 L.Ed. 414 (1945).
received the opprobrium it deserves In the same vein, and more recently, the
when used as an excuse for ignoring the Supreme Court, Justice Scalia writing,
law. said, "Courts may not create their own
limitations on legislation, no matter
Professor Dickerson, one of the early how alluring the policy arguments for
writers on statutory interpretation, doing so,...." Brogan v. United States,
described the process of purpose- 522 U.S. 398, 118 S.Ct. 805, 811-12,139
inventing as if he had this case in mind: L.Ed.2d 830 (1998).
In support of its position, the court
As with legislative cites various pieces of what it describes
intent, the danger in as legislative history. However, a
presuming an actual prerequisite to judicial use of legislative
legislative purpose history, even relevant legislative
beyond what is history, is a finding that *1382 the
expressly or impliedly statute at issue is ambiguous. "Our
revealed is that the first step in interpreting a statute is to
interpreter will either determine whether the language at issue
attribute to the statute has a plain and unambiguous meaning
a purpose of his own with regard to the particular dispute
contriving or search in the case. Our inquiry must cease if
for actual purpose so the statutory language is unambiguous
relentlessly that he and `the statutory scheme is coherent
goes beyond the limits and consistent.' " Robinson v. Shell
of the appropriate Oil Co., 519 U.S. 337, 117 S.Ct.
available evidence. 843, 136 L.Ed.2d 808 (1997) (Justice
Thomas, writing for a unanimous
Court) (quoting United States v. Ron
Reed Dickerson, The Interpretation and Pair Enters., Inc., 489 U.S. 235, 240, 109
Application of Statutes 92 (1975). S.Ct. 1026, 103 L.Ed.2d 290 (1989)). To
the court's credit here, the majority does
Writing more formally for the Court a not pretend to find in this unequivocal
half-century ago, Justice Jackson said, statute any ambiguity. Rather, it
"we take the Act as Congress gave it simply concludes that committee report
to us, without attempting to conform it language, nowhere addressed to the
to any notions of what Congress would specific problem before us, trumps
have done if the circumstances of this statutory clarity. 6
case had been put before it." Western
Union TeL Co. v. Lenroot, 323 U.S. 490,
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 20
EFTA00797894
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
The committee report language the the very next sentence in the Report
court cites includes certain 1988 House is: "Nothing in this section shall be
and Senate reports. In the first place, construed to affect the requirements
this so-called legislative history is not of section 8118 of the Department of
history - that is, the House and Senate Defense Appropriations Act, 1988." Id.
Reports the court cites with such
authority (see maj. op. at 1374-75)
were written after § 8118 was enacted
3.
in 1987, and relate to later-considered
legislation. How the views of a later The court finds further justification
Congress, not contained in actual for its emasculation of the statute
legislation, can be seen as amending or by opining that "Congress can not
modifying prior legislative acts, is not have intended to charge the contracting
explained. And, even assuming that any partner with adverse consequences
of that legislative history is relevant to depending on whether the Defense
understanding the 1987 Act, the only Department carried out the internal
consistent thread in all of it is the responsibilities and filed the reports
expression of congressional irritation that Congress required." Slip op. at
and frustration with the DoD's (or at 1375. The response to that observation
least the Navy's) stubborn insistence on is that that would appear to be exactly
doing what Congress wanted stopped. what Congress intended. AT & T, one
of the country's leading government
Further, when examined, even the
contractors, 7 could be expected to be
terms in which the language of the 1988
familiar with government contracting
Senate Report was written, heavily
laws. It is difficult to imagine that AT
relied upon by the court to support
& T was unaware of the battle between
its conclusion, see maj. op. at 1375,
Congress and the DoD *1383 over
fail to support the court's view. The
these fixed price-type contracts. At the
Report states that "this section [not
least, it is not irrational for Congress
8118 of the 1987 Act, but a later-
to have assumed that a contractor, like
proposed section] not be used as the
AT & T, proposing to undertake a
basis for litigating the propriety of an
major R & D contract would know who
otherwise valid contract." S.Rep. No.
in the DoD to contact regarding the
100-326, at 105 (1988). Since by its
requirements for the contract they were
terms a contract in direct violation of
negotiating, and that the DoD's lawyers
8118 is not "otherwise valid," the
would know the relevant law.
statement proves nothing with regard to
8118, whether it be the 1987 version
What the court seems to have in mind
or the proposed 1988 version. And in
here, though it does not say so, is
case a court should miss that point,
the rule, sometimes called the "Golden
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 21
EFTA00797895
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
Rule," that a statute should not be Emphasizing the narrow scope of the
understood to call for an absurd result. absurdity exception, Justice Kennedy
Just as finding a statute ambiguous went on to note:
permits a court to go beyond the terms
of the statute in searching for meaning,
the Golden Rule permits a court to Where it is clear
go beyond the apparent meaning of a that the unambiguous
statute when its application would be language of a statute
absurd. embraces certain
conduct, and it would
Justice Kennedy described the Rule not be patently
thusly: absurd to apply
the statute to such
Where the plain language of conduct, it does not
the statute would lead to foster a democratic
"patently absurd consequences," that exegesis for this Court
"Congress could not possibly have to rummage through
intended," we need not apply the unauthoritative
language in such a fashion.... This materials to consult
exception remains a legitimate tool of the spirit of the
the Judiciary, however, only as long legislation in order to
as the Court acts with self-discipline discover an alternative
by limiting the exception to situations interpretation of the
where the result of applying the plain statute with which
language would be, in a genuine the Court is more
sense, absurd, i.e., where it is quite comfortable.... The
impossible that Congress could have problem with spirits
intended the result, and where the is that they tend to
alleged absurdity is so clear as to be reflect less the views of
obvious to most anyone. the world whence they
come than the views of
Public Citizen v. United States Delis
those who seek their
of Justice, 491 U.S. 440, 470, 109
advice.
S.Ct. 2558, 105 L.Ed.2d 377 (1989)
(Kennedy, J., concurring). One must
wonder whether a statute that orders Id. at 473, 109 S.Ct. 2558 (internal
the DoD not to spend money in a citations omitted) (Kennedy, J.,
wasteful way is "absurd" within the
concurring). 8
definition set forth by Justice Kennedy.
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 22
EFTA00797896
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
Actually, the right answer is not that
difficult, even accepting the fact that
4.
there is no legally-enforceable contract
AT & T has no rightful claim to between the parties. AT & T argues
another penny of public money. It that, since the contract it made is
agreed to build and sell a product to unenforceable, it should be treated as
the Government for a fixed price. It having an "implied-in-fact" contract, a
performed its end of the deal, and key term of which would be different
delivered the goods. The Government from that to which the parties actually
likewise performed its part of the deal; agreed. The different term would be
it paid AT & T the agreed-upon price that the contract would not be for a
(actually more, as a result of negotiated fixed price, but instead would be a
add-ons). cost-plus contract. That would take the
contract outside the scope of§ 8118, and
If the contract had been valid under give AT & T a rightful claim to all the
governing law, AT & T would have money for which it asks.
no basis for claiming more money;
our precedents are unequivocal that That would also make nonsense out
full payment *1384 under a valid of the concept of an implied-in-fact
fixed price-type contract is all to which contract. An implied-in-fact contract
is a form of consensual contract,
a contracting party is entitled. 9 The
reflecting the basic requirements for
risk of loss for misjudging what it
such a contract including that of a
takes to perform, or for deliberately
meeting of the minds. It differs from
underbidding, is on the contractor, not
the usual express contract only in that
the Government. 10 the terms, instead of being expressly
stated by the parties, are derived from
AT & T now seeks to take advantage their conduct. Nothing here in the
of the fact that the deal it made conduct of the parties suggests an
with the Government did not result agreement to have a cost-plus contract;
in an enforceable contract, which it on the contrary, the parties specifically
likely knew (and certainly should have stipulated to a fixed price-type contract.
known) when it proposed to enter into
the agreement. AT & T demands more If AT & T is to have any remedy
money for what it has been fully paid entitling it to more than what it has been
to do. The answer to that facially paid, its claim must be based on some
nonsensical demand is, in a word, "no." sort of equitable claim for payment for
goods sold and delivered, a quantum
Perhaps the court thought it could not
valebat claim." Even assuming for
get there if, in accordance with the
discussion purposes that the Court
statute, it held the contract invalid.
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 23
EFTA00797897
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
of Federal Claims could exercise the wasteful, or simply ignorant contractor
powers of a court of equity, AT & T cannot foist off on the other contracting
has no equity on its side, and therefore party the consequences of its own
is not entitled to the intervention of a incompetence. 12 The law in a case like
court of equity. this leaves the parties where it found
them. 13
AT & T comes to the court with unclean
hands. AT & T is not an innocent
The en banc court appears unwilling
bystander being taken advantage of
to give AT & T any more money
by a predator government. Both the
on its so-called non-contract claim. As
Government and AT & T knew exactly
I said at the beginning, a court has
what they *1385 were doing when they
a responsibility to arrive at the right
entered into this deal. It simply defies
result, but also an obligation to do
belief that AT & T was unaware of
no harm to the fabric of the law. A
8118 when it purported to contract
wrong result is an injustice to one party;
with the Government or was unaware
distorting important legal principles is a
that the Navy was proceeding with the
disservice to the entire legal system.
contract in the manner the Navy did.
It is true that statutory interpretation
In any event, that does not matter. The
does not occur in a vacuum. Words
most that AT & T would be entitled to
take meaning from the context in which
under any equitable theory is the fair
they are used, and, when text and
value of the goods sold, and that value
context yield genuine doubt, courts may
was agreed to by AT & T when it made
seek guidance from accepted canons,
the deal with the Navy. The goods are
from history, and from legislative
one-of-a-kind, not to be found on the
purpose when it can be authoritatively
shelf at your usual military equipment
known. In many cases, construing
supermarket. There can be no better
Congressionally-mandated language is
method for determining a fair price for
as much an art as it is linguistic science.
the goods than to see what a willing
But it is not an art in which the picture
seller would sell them for to a willing
that emerges is without constraints, or
buyer.
is limited only by the imagination of the
artist.
AT & T does not allege that it was
coerced by the Government, or that
There is an established methodology
it was caused to enter into the deal
that courts employ in construing
by fraud. It simply wants more money
statutes. As the quoted excerpts
for a product it agreed to provide
from the Supreme Court show, the
for a price that proved, according
methodology is well-recognized, even
to AT & T, too low. An inefficient,
if judges do not always agree on how
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 24
EFTA00797898
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
much weight to give to its various parts case would not require an absurd result,
there is neither reason nor justification
in a given case. 14 The methodology
for reaching beyond the statute to
is designed to provide guidance
legislative history or supposed purpose
*1386 for the exercise of judicial
in order to find a different answer.
self-discipline, the self-discipline that
Further, what little known legislative
produces principled decisions.
history there is I find inapposite and
unpersuasive. Accordingly, I believe it
This court has in the past expressly
is our duty to apply the statute as it has
recognized the governing principles:
been given to us by Congress.
"A statute is by definition the
law to be followed—not disregarded,
Thus, my answers to the questions
effectively repealed, rewritten, or
certified are: (1) yes, the contract is
overruled (unless unconstitutional)
null, void, and necessarily invalid, as
—in the federal courts," In re
the Court of Federal Claims correctly
Mark Indus., 751 F.2d 1219, 1224
concluded; and (2) no, AT & T is
(Fed.Cir.1984), and recently reiterated
not entitled to any equitable or other
the point: "This court is empowered to
remedy on the facts presented, even if
rewrite neither statutes nor regulations,
the Court of Federal Claims had power
however unwise, nor does it have the
to grant such a remedy. I respectfully
information base nor expertise to do so
dissent from the court's contrary view.
effectively," Newport News Shipbuilding
& Dry Dock Co. v. Garrett, 6 F.3d 1547,
1558 (Fed.Cir.1993). All Citations
In sum, since the statute before us is not 177 F.3d 1368
ambiguous and its application to the
Footnotes
* Circuit Judges Rich and Michel did not participate in this decision.
1 The panel decision of the Federal Circuit, reported at American Tot & Tel. Co. v. United States, 124 F.3d
1471 (Fed.Cir.1997), was vacated and withdrawn, 136 F.3d 793 (Fed.Cir.1998). The decision of the Court of
Federal Claims is reported at 32 Fed.Cl. 672 (1995), and the certification for interlocutory appeal is reported
at 33 Fed.Cl. 540 (1995). On this rehearing amicus briefs were filed by the Federal Circuit Bar Association
and by the Electronic Industries Alliance and Aerospace Industries Association of America.
2 The dissenting opinion would hold the fully performed AT & T/Navy contract void ab initio, stating that the
purpose of § 8118 was to "prevent contracts with the United States in contravention of its terms". However,
Congress' stated concern was to curb the Navy's use of fixed price R & D contracting so as to "maintain
the government's credibility as a reliable business partner: H.R. Conf. Rep. No. 100-498 at 623 (Dec. 22,
1987), not to bar essential defense procurement. The dissent's proposed nullification of this fully performed
contract would do little for "the government's credibility as a reliable business partner:
1 A similar reaction was eloquently expressed by Chief Judge Joseph of the Oregon Court of Appeals in an
award to his colleagues. See Western Communications, Inc. v. Deschutes County, 100 Or.App. 706, 788
P.2d 1013, 1017 (Or.App.1990) (Joseph, C.J., dissenting-In-part, concurring-in-part).
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 25
EFTA00797899
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
2 CI. Rust v. Sullivan, 500 U.S. 173, 111 S.Ct. 1759, 114 L.Ed.2d 233 (1991) (construing the phrase -method
of family planning" in an Act appropriating funds to the Department of Health and Human Services. subject
to a proviso that stated: "None of the funds appropriated under this subchapter shall be used in programs
where abortion is a method of family planning.").
3 See Omnibus Consolidated Rescissions and Appropriations Act of 1996, Pub.L. No. 104-134, 110 Stat.
1321-298.
4 Judge Wald dissented. She did not disagree with the court's understanding of the consequences of
noncompliance with the statute, but dissented on the grounds that the state official's letter was "the functional
equivalent" of a governor's letter. See Harbor Gateway, 167 F.3d at 607 (Wald, J., dissenting).
5 As my colleagues know, I spent some years of my life as a sea-going officer in the U.S. Navy; it is not easy
for me to be critical of the Service, but the facts are what they are.
6 The concurring opinion stays within established statutory interpretation principles by attempting to redefine
the scope of § 8118. Unfortunately, for the reasons well-explicated in the opinion of the court majority, the
attempt to have this contract escape the clutches of § 8118 fails.
7 For the year 1987, AT & T was listed as 15th among the Top 100 Federal Contractors, with
1,438 procurement actions worth something over $2 billion. See Federal Procurement Data Center,
Govemmentwide Information Systems Division, MVS. GSA, Central Office, Top 100 Federal Contractors
14 (Jan. 25, 1988). AT & T was 16th in 1988. See Federal Procurement Data Center, Governmentwide
Information Systems Division, MVS, GSA, Central Office, Top 100 Federal Contractors 14 (Feb. 2, 1989).
8 Justice Rehnquist expressed the same sentiment in United Steelworkers of America v. Weber, 443 U.S. 193,
254, 99 S.Ct. 2721, 61 L.Ed.2d 480 (1979) (Rehnquist, J., dissenting) (-Finding the desired result hopelessly
foreclosed by these conventional sources, the Court turns to a third source —the 'spirit' of the Act. But close
examination of what the Court proffers as the spirit of the act reveals it as the spirit animating the present
majority, not the 88th Congress.").
9 See, e.g., Loral Corp. v. United States, 193 Ct.CI. 473, 434 F.2d 1328, 1330 (1970) ("Mho type of contracts
in question are firm fixed-price contracts and once the price was agreed upon, that price remains fixed and
it is not subject to further negotiation, unless otherwise provided in the contract.'); see also 48 C.F.R. §
16.202-1 ("A firm fixed-price contract provides for a price that is not subject to any adjustment on the basis
of the contractor's cost experience in performing the contract."); cf. ITT Fed. Servs. Corp. v. Widnall, 132
F.3d 1448, 1451 (Fed.Cir.1997) (holding that ITT was not entitled to recovery of normal severance costs
because in a firm, fixed-price contract situation, the contractor assumes responsibility for all such costs that
may be incurred).
10 See, e.g., ITT, 132 F.3d at 1451 (Fed.Cir.1997) (agreeing with the ASBCA that in a firm fixed-price contract
situation, the contractor "assumes maximum risk and full responsibility for all such costs that may be
incurred"); see also 48 C.F.R. § 16.202-1 (placing upon the contractor "maximum risk and full responsibility
for all costs and resulting profit or loss"); Emerald Maintenance, Inc. v. United States, 925 F.2d 1425,
1430 (Fed.Cir.1991) (noting that the risk of loss was on the contractor who "should not be compensated for
incurring added expenses resulting from assuming that risk").
11 An action for goods sold and delivered, "founded on an implied assumpsit or promise, on the part of the
defendant, to pay the plaintiff as much as the goods were reasonably worth." Black's Law Dictionary 1244
(6th ed.1990).
12 It should be obvious that, just as AT & T could not claim additional payment for goods for which it has
been fully paid, it could not claim ownership of the goods for purposes of recovering them, for example, in a
replevin action. A suggestion to the contrary could not be taken seriously. Even if the law would contemplate
it, it is hard to imagine a major American contractor, whose fiscal lifeblood comes in substantial measure
from contracts with the United States Government, even thinking about replevying a secret government
weapon for resale elsewhere. Money is one thing; fiscal suicide is another.
13 See, e.g., Keystone Driller Co. v. General Excavator Co., 290 U.S. 240, 245, 54 S.Ct. 146, 78 L.Ed. 293
(1933) ("A court of equity acts only when and as conscience commands; and, if the conduct of the plaintiff
be offensive to the dictates of natural justice, then, whatever may be the rights he possesses, ... he will be
held remediless in a court of equity." (internal quotations omitted) (quoting Deweese v. Reinhard, 165 U.S.
386, 390, 17 S.Ct. 340, 41 L.Ed. 757 (1897))).
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 26
EFTA00797900
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
14 The methodology of statutory interpretation, with all its ramifications, has become one of the darlings of
academic discourse, and is offered as a proper subject of study in many of the leading law schools, taught
from modem-day casebooks. See, e.g., William D. Popkin, Materials On Legislation: Political Language and
the Political Process (Found Press 2d ed.1997); William Eskridge & Philip Frickey, Cases and Materials
on Legislation—Statutes and the Creation of Public Policy (West Pub. Co.2d ed.1995); Abner Mikva & Eric
Lane, Legislative Process (Little, Brown 1995).
End of Document O 2019 Thomson Reuters. No claim to original U.S. Government Works.
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 27
EFTA00797901