Kyle W Reavis
Construction Manager
Little St James / Greater St James
Congratulations:
This letter is to serve as an invitation to bid for the scopes of work listed below on Either GSJ or
LSJ. You need to provide start dates, scope item duration, that will be included in the project
schedule. Any issues with procurement of materials or schedule impacts must be presented
immediately as to no effect other trades or the scheduled opening of the project.
Job Name: "Flag Pole Pool"
The SCOPE OF WORK to price is as follows:
• Demolition of Existing Pool Shelter
• Construction of New Pool Shelter (20'x40')
• Design of New Shelter
• Painting by Owner (Include as Add / Alt)
Delays or cost impact submitted will be reviewed and rejected, or accepted as a change order
with directions on how to proceed issued by the CM.
Sincerely,
Kyle W Reavis
' nager LSJ - GSJ
EFTA00802115