From: Richard Kahn <:a>
To: "jeffrey E." <jeevacation@grnail.com>
Cc: Leighton Allenby
Subject: Lutron
Date: Tue, 18 Aug 2015 13:51:48 +0000
i spoke with Al and they were going to begin pulling the panels on 2nd, 1st and 4th floor tomorrow wednesday
aug 19th
they are ok to begin on monday aug 24th based on your upcoming visit since once that begins it will be a solid
week of no lights
new estimated date is sep 4th however they may need to do some minor tweaking week of sep 7th
menvin sent 3 emails showing protection that has been laid (will send next)
please advise if they should pull protection and if so on which floors
thank you
Richard Kahn
HBRK Associates Inc.
EFTA00848405