From: Ann Rodriquez
To: jeevacation@gmail.com, Rich Kahn
Subject: WAPA Update
Date: Thu, 04 Jan 2018 16:46:07 +0000
Inline-Images: image ljpeg; image2.jpeg; image3.jpeg; image4.jpeg; image5jpeg; image6jpeg;
image7.jpeg; image8.jpeg; image9.jpeg; imagel0jpeg
Bryan's electric guys confirmed 2 days of Splicing & getting the new Manhole in. If the same crew that worked
today come back out on Saturday we "might" be able to have WAPA on Monday
gJimage1 jpeggjmageljpeg2imageljpegglimage4jpeggimage5jpeg2image6jpegmage7jpeg
gJimage8jpeggjmage9jpegg2,image1 0jpeg
Ann R.
Begin forwarded message:
From: Hugo Hodge
Date: January 4, 2018 at 10:27:27 AM AST
To: ,Ann Rodriquez < >,
Subject: LSJ
Good morning All,
We have started the work on LSJ. From my initial estimate, it will take 2 full days to get the cable spliced with
the new manhole in place. Once that takes place tomorrow we will then test the cable (Hi-Pot test) and then
leave the cable energized for at least 24 hours. After that period, we will then go through the steps to put LSJ
back on WAPA's Grid.
HH