From: Marc Dober
To: Gary Kerney -4
Cc: jeffrey epstein leevacation@gmail.com>
Subject: Re: K&S Subcontractor no-show
Date: Thu, 17 Nov 2011 00:15:42 +0000
We have not got to that part of discussing design. If they are approved to come over we will go over the design.
We then can make a decision to send them back with specs and they build it in PR and bring it over.
Bottom line is that way to much millwork was put on the shoulders of K&S. I know I am new at this but how did
anyone expect them to get everything done in the first place. By him not showing up today, really bothers me
especially in that we are critically trying to get this area done for an arrival on Tuesday, and he knows what we
are up against.
We finally got in touch with him late this afternoon and he says he will be here tomorrow but I won't believe till I
see him on the crew boat.
I am looking at all the invoices he has submitted along with change orders to try and make sense of it all. Why
no retainage on his work is my first question as we could of protected ourselves to a point with that money?
I apologize for being Monday morning quarterback but I call them like I see them and I agree they do great work
at a good price but there are additional costs that come with dealing with a sub like this.
Have a good evening
Marc
On Nov 16, 2011, at 7:19 PM, "Gary Kerney" < > wrote:
I believe we bought the 2 1/2 thick frame material as part of the contract with k&s. 1,700?
Do the pr workers understand the design. Extra thick frame and 3" louvers I think the lover doors have to be
made in a millwork shop and fitted to our onsite frame
Sent from my iPhone
On Nov 16, 2011, at 5:37 PM, "Jeffrey epstein" <jeevacation@gmail.com> wrote:
199
Sony for all the typos .Sent from my iPhone
Begin forwarded message:
EFTA00924710
From: Marc Dober
Date: November 16, 2011 4:15:48 PM EST
To: Jeffrey Epstein leevacation@gmail.com>
Cc: Richard Kahn <I thomas melnick
Subject: Re: K&S Subcontractor no-show
Jeff,
As a follow up to this:
Here are some numbers :
To date we do not owe K&S anything currently. They need to finish some work that was not completed.
We have a pending change order that has NOT been approved for $9,730 for manufacture breezeway doors
and to manufacture the shutters for the chillax bathroom. We also have a change order for to redo the
bathroom windows and the additional breezeway doors plus installation of both for $10,600.
At this point we should not put up with the BS K&S is giving us. Yes, they do good work but they show up
when they want to which is unacceptable especially when we have a tight deadline.
My contact in Puerto Rico can have two very highly skilled millworkers over here tomorrow for $9k for
40hrs of work ($75 /hour ), airfare (approx. $600), per diem ($35/ day), and 15% overhead/profit ($1k),
accommodations would be about $400.
We would put these two guys on getting the chillax bathroom, breezeways doors done.
Marc
Jeff,
The K&S guys did not show up this morning and wanted to propose bringing in two guys from a company
that have dealt with in Puerto Rico. With this guy not showing up, the millwork that still needs to be
completed by the time of your arrival won't be done.
I am getting the pricing together now and have the two guys on hold awaiting the approval. We will bill
back K&S for this as he knows this is crunch time and not to show up is unacceptable.
Please let me know if this ok to proceed.
Thanks
EFTA00924711
Marc