From: Larry Visoski
To: Je vacation <jeevacation®gmail.com>
Cc: Rich Kahn
Subject: Gulfstream Wood veneer 7039407 R00.pdf
Date: Thu, 12 Oct 2017 16:09:15 +0000
Attachments: 7039407_R00.pdf
Jeffrey
Attached is Veneer quote:
Gulfstream can accomplish wood veneer you selected,.
Price $702,649.00
Down time estimate is 65 -75 working days. (Not including weekends, thats OT).
Rerun to service would be as originally announced Jan 26th, with New veneer.
Rusty informs all service centers loose manpower during Thanksgiving, Christmas and NewYears,,, he estimates
their shop looses 2 weeks of manpower since Mechanics take vacation and extra Days, since work weeks are
reduced.
The best scenario is Jan 26 completion„ could be earlier, but he doesn't want to promise you a date he can't
keep.
Current schedule is:
1-Input to Service Center Oct 23rd
2-Install KA wifi and Xm weather plus some light maintenance to clean up DUE list, remove Veneer if approved.
3-aircraft moved to Paint prep Nov 29th
4-Plane goes in Paint hanger Dec 4th
5-Dec 24th plane is back at Service center.
6-Jan 5th return to service if Veneer is not approved.
7-Jan 26th return to service with NEW veneer installed (If Approved).
Gulfstream needs to know as soon as possible to get veneer ordered,
***Please advise if you approve of veneer installation?
Thx,
Lany
Sent from my iPad