Mr Epstein,
Helicopter Pad will be 97 Yards (100' x 4"). That would be on a level grade and we can get back-fill from GSJ
and compact ourselves. I think we should look into pour breaks to prevent EB from getting overwhelmed trying
to pour 100 yards in one day. If their are any issues with Barges on pour-day we will have non-structural pour
breaks that will result in major cracking. Maybe do (3) 34 yard pours on separate days. To join the separate
sections you just need 2' pieces of #4 rebar core drilled and epoxied into the joints. That will produce a clean
structural joint.
Very Respectfully,
Kyle Reavis
On Thu, Aug 16, 2018 at 5:14 AM, Jeffrey E. leevacation@gmail.com> wrote:
kyle please detail for me your concrete calculation for heli area thx. , I want the sundial completed by tues, .
jules should be wrking pebble beach rip rap. . , as i wil be with new archtects on the eve of 25th dock pour
MUST be done by them. .1 want a delivery date on the rebuiilt generator parts , having no backup is a
problem. . lets look at adding a brand new 150k generator as the 2 big ones are oversized. I want a
schedule of the bathroom complettions. for the cabanas. thx.
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation®gmail.com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA01008184