ATM Reports: Executive Summaries
Island Global Yachtin Ltd. • • Fort Lauderdale, FL 33301
Tel: • Fax: • www.islecap.com
EFTA01119824
Marina Due Diligence Assessment
Simpson Bay Yacht Club Marina
St. Maarten, N.A.
DRAFT EXECUTIVE SUMMARY
Prepared For
Island Global Yachting
Ft. Lauderdale, Florida
NOVEMBER 15, 2006
EFTA01119825
EXECUTIVE SUMMARY
A marina assessment was conducted by Applied Technology & Management, Inc. for Island Global
Yachting to assist with the review of the facilities at Simpson Bay Yacht Harbor, St. Maarten, NA The
review concentrated specifically on the items of condition of the existing physical facilities and
environmental issues. The major features on this site include the marina, a two-story condominium
office building, separate gate houses, a restaurant and outdoor eating area, a fuel dock building and a
maintenance shed.
Marina Engineering Summary
Overall, the property is in fair condition. It appears that regular maintenance has been conducted on the
upland elements, but the docks/piers and utilities are showing some significant deterioration and
deferred maintenance, particularly for a facility that was initially constructed in 1989 (17 years ago).
ATM conducted an engineering evaluation of the marina structures and utilities. The following highlights
the findings of this effort.
> Site Exposure - The marina docks and amenities are generally well-protected from prevailing
environmental forces. Simpson Bay is sheltered from the effects of offshore wave conditions:
therefore, only wind-generated waves within the bay can affect the site. Snoopy Island and the
Bay geometry limit exposure to the NNE through SE directions. The slips are largely oriented
ENE-WSW direction, which is generally bow into the prevailing winds. Tides in Simpson Bay
average 1 ft Storm surge during hurricanes can increase water levels on the order of 1 m,
according to regional reports by Alicyon. The most exposed slips (megayacht med-moors)
would be anticipated to be unoccupied during hurricane season, although reports from
previous storms (Lenny, Luis, etc.) indicate that smaller vessels remained in the marina.
➢ Navigable Depths and Sedimentation Potential — Sedimentation in the marina basin has
historically only been a localized problem and is believed to be primarily due to stonnwater
runoff carrying sediments into the marina basin from the surrounding areas and effects of
significant tropical storms. According to the marina operators, the basin has only been
dredged twice in the past 8 years. Records received from the owners were limited; however,
they indicated dredging of -6,000 cy in 2003 to deepen the entrance approach behind Snoopy
Island and 31,000 cy in 1999. Over the effective plan area of the marina and immediately
surrounding channels (- 10 acres), this equates to less than 0.25 ft/yr accumulation.
Three depth surveys provided by SBYC dated December 21, 2001 and July 25, 2003 were
compared with a spot sounding check by ATM on September 26, 2006. The SBYC surveys
are in feet assumed relative to low water datum. ATM corrected our lead line soundings to
approximate low water based on predicted tides at St. Barthelemy. Comparison of ATM to
the SBYC surveys reveals slight changes in the recorded mean low water depths, notably
some shallovving in A Dock and NB fairway areas. Docks B and C appear more stable.
Marina management reports the need for some maintenance dredging in 2006. ATM's survey
check indicated some areas of 7.5-10 ft under A Dock, with depths in the med-moor area of
12-16 ft. This should be included in the present owner's operating budgets and should be
confirmed.
An issue for future maintenance dredging is disposal of the materials. Previous events had
included material disposal on Snoopy Island, which resulted in lower unit costs of $5-7/cy. The
requkement to dispose of material offshore could easily increase unit dredging costs to
$20+/cy.
1
EFTA01119826
• Shoreline Stabilization — The shoreline within the property limits extend approximately 300 ft.
The shoreline is stabilized with a mix of cast-In•place and precast concrete panels. Specifics
of the construction were not determined, but it appears to be in average/fair condition. Low
water depths are generally less then 3 ft along the west portions of the shoreline. Dredged
depths approach 9-10 ft along the east portion of the shoreline, where larger vessels berth
adjacent to the high-speed fuel dispenser. There was no apparent loss of soil observed along
this deeper portion of the shoreline. The shoreline structures should be monitored frequently
for any potential failures and/or safety concems to pedestrians and repairs made promptly.
> Manna Structures Overview - The marina consists of fixed concrete docks supported by
reinforced concrete pile caps (painted blue) and driven concrete piles. Dock main walkways
and fingers have a precast and poured in place concrete decking surface with integral utility
raceways. The raceways are accessed via cast concrete panels in the deck. Portions of the
decks are dressed with ceramic tile inlays and different concrete finishes.
The site visit consisted of observation from the fixed docks as well as by inflatable tender,
which was provided by the marina. ATM also reviewed previous structural assessment reports
by CCS who conducted a personal inspection of the property in August 2005. The facilities
were reported to be generally in average condition with minor instances of deferred
maintenance noted during the inspection.
Based on our observations, the docks appear to be in poor condition. Several concrete piles
and pile caps are missing and/or are deteriorating, leaving the steel rebar exposed and
vulnerable to corrosion and loss of structural strength. The concrete surfaces of the docks are
cracking and in some areas leaving holes and potential tripping hazards, particularly where the
utility chase covers are cracked or broken.
> Marina Utilities Overview— The marina offers three phase and single phase shore power in a
variety of configurations. Power is provided to the dock systems from two different
Government transformer vaults. One vault provides 480 volt, three phase power to Dock A,
while the other provides 208/120 volt three phase power to Docks B, C, and the upland
development. Power distribution and condition for the upland elements appears generally
adequate, with the exception of some potential safety issues related to exposed/loose tree
wiring at Jimbo's. This wiring should be further inspected for safety compliance.
During the site visit, approximately 19 different types, styles or configurations of power
pedestals were observed as being used on Docks A, B and C. Dock A has been renovated
several times during the last 5 years in order to provide power that will accommodate the
larger yachts. All wiring as well as the power pedestals are relatively new and therefore are in
good condition. The only discrepancy noted was the fact that the total amount of power
available to dock A via the power company's 600 kva transformer is far less than the total
connected load of approximately 1100 ova. Wiring and pedestals on Dirks B and C are more
varied and in fair to poor condition. Significant dock electrical system issues are as follows:
• The most dangerous situation identified during our site visit was the cable taps and
splices that have occurred in the cable trenches. The leakage of electrical current
through these deteriorated splices not only causes damage to the boats through
electrolysis, It also poses a life threatening situation to people that might be in the water
working on their boats or walking barefoot on a wet dock. The repair of electrical taps
and splices in the cable trenches is of paramount importance to life safety. There are an
estimated 150 cable splices and taps located primarily on Dirks C and B that should be
replaced.
2
EFTA01119827
• Many of the boats that had plugged into the pedestals with their power cabling have
created unsafe conditions. The extensive use of plug adapters and undersized cabling
pose a fire hazard by potentially overloading the cables to the boats. In more than one
case, a 16 gauge extension cord (rated at 13 amps) was plugged into a 50 amp
receptacle.
• Replacement and repair of the broken power pedestal equipment would prevent further
damage to the pedestal and perhaps avdd an electrical accident Approximately 17
pedestals were identified as needing minor repairs that would include replacing
mounting bolts, replacement of circuit breakers, and replacement of broken receptacles.
• As pedestals are being replaced, the newer ones are usually provided with multiple
power and voltage configurations that would have the potential to overload the existing
circuits. A load survey of all existing circuits should be made during peak season to
determine the existing capacity of electrical system to the docks. This load survey
should be accompanied by an accurate single line diagram showing the locations and
sizes of cabling, supply transformers, fuses and protective circuit breakers. The results
of this survey along with projections of future boat types and ac-cociated power
requirements would dictate the extent of renovations that can be made to the existing
dock system.
• Design of a new distribution system with added capacity for the larger boats (mega
yachts) would be very difficult due to the limited space within each dock system where
cables can be routed. Most of the cable trenches are completely filled and so additional
means would be required in order to provide a new or increased capacity to Drinks B
and C.
There is no marina pump out available and as such this promotes dumping in the marina
basin. However, when evaluated against the stormwater/sewer outfalls present in Simpson
Bay, this does not present a significant water quality issue Potable water is provided at the
pedestals and metered. Diesel and gasoline are provided at the fuel dock and diesel is also
provided at a dispenser east of the main dock arrpcs. Water and fuel utilities are discussed
further in the environmental section below.
➢ Layout and Potential Expansion - The marina reports 120 slips. ATM's review indicates a total
of 6,820 If of leasable space (including 2 unavailableJowned slips C22 and C24). This includes
berthing for approximately 16 megayachts (> 80 ft) and 98 small craft. The marina layout and
fairways are generally adequate for current marina operations. By current minimum fairway
standards, the interior double loaded slips are limited to 50-55 ft WA, although the widths of
these slips are narrower than current standards. The slip widths at 30-32 ft were likely sized
by 1980s standards for 35-40 ft sailboats. The majority of vessels are sailboats under 50 ft.
Some catamarans require wider berths and currently occupy two slips, and it is assumed that
marina management needs to selectively berth vessels exceeding 35-40 ft to allow adequate
berthing width in the double loaded slips.
It is noted that with future pier reconstruction comes the opportunity for reconfiguration of the
marina basin. Though the facility may be adequate for current usage, accommodation for
additional large slips is possible to provide berthing for larger yachts and wider sailboats
(catamarans). The megayacht med-moor arrangement could be improved with alongside
berthing in future expansions.
➢ Recommendations and Deferred Maintenance Cost Estimate — The marina's oldest
components are 17 years old. Though some maintenance and improvements have occurred,
the marina piers and electrical system have some significant problems that need attention.
General cost estimates for immediate repair (life-safety), 0-5 year repair/replacement, and
complete replacement (more than 5 years into the future) of the marina is attached. This
3
EFTA01119828
represents in-kind replacement (with appropriate updates, inclusion of pumpout, etc.) and does
not include reconfiguration or expansion.
In addition, the following items are generally minor in nature and most can be handled with in-
house staff or local contractors, as part of normal facility maintenance:
C• Add safety ladders at miscellaneous locations around the marina basin.
• Monitor condition of power and water pedestals annually. Reattach loose pedestals
to the decking with proper bolts. Replace any inoperable elements or replace
pedestals as necessary.
▪ Replace cracked and broken concrete trench/utility access covers. These create
potential tripping hazards for pedestrians.
Continue general monitoring and replacement program of loose or damaged cleats
and bollards, focusing on the large vessel docks (A Dock).
4. Consider addition of more fire suppression equipment (i.e., portable foam and water
cart, similar to those found at wivw.marinafires.com or similar. One cart should be
maintained at the foot of the docks. Add extinguishers per NFPA 10 requirements at
nominally 150 ft intervals along the docks.
It should be noted that deficiencies highlighted above were identified during this site investigation and
interviews with the marina staff. Immediate expenditures indicate repairs or deficiencies, which pose a
danger to public safety or are in violation of good practice. Also, if year 1-5 maintenance items are left
uncorrected, these can lead to further deterioration of the facilities and increase corrective repair costs.
This may also lead to a decrease in occupancy and impact marketability. Items noted should be
handled on a priority basis, with life safety issues taking precedence over routine preventative
maintenance.
Upland Structural Engineering Summary
The Simpson Bay Yacht Club site includes a two-story condominium office building, two gate houses at
the entrance into the dock area, a maintenance/storage facility, a bar/restaurant with outdoor pool area,
and a building at the end of C Dock that houses the fuel dispensing operation.
The buildings have sloped metal roofs which are covered with red barrel tiles or corrugated FRP and
shingles that are supported by concrete or wood framing. The ceiling of the bottom floor of the two-story
condominium office building is constructed of suspended metal grids supporting acoustic ceiling tiles.
The exterior of the buildings consists of concrete walls and concrete masonry block covered with
painted stucco. The floors are concrete or wood decking and some are finished with ceramic tiles. The
restaurant building stricture consists of timber framing and corrugated FRP and shingle roofing. The
wooden floor deck has several elevated wooden seating areas.
2-Story Condominium Office Building - The -1,560 sq ft marina main office is located within the
condominium office building, which is adjacent to the main pier. There is exposed rebar
apparent along the ceiling on the second floor of the West side of the building. Evidence of
water stains is apparent along the first and second floor ceilings on the East side of the building.
➢ Gate Houses - Located near the marina entrance there are two separate 480 square foot gate
house buildings, separated by a covered walkway. The East gate house building is occupied by
the Dociunasters Office and the West gate house is rented by a yacht charter service. The roof
of the East gate house appears to have had some repairs attempted due to a leaky air
conditioning unit. There are also some water stains evident on the ceiling. The floor was
constructed too low (same level as exterior) and reported to develop puddles during storms, as
4
EFTA01119829
several cracks were also noted. The concrete floor in the West gate house has some cracks
and holes that need to be sealed and the window exterior needs to be refurbished.
> Jimbo's Bar (4 Restaurant — The restaurant was constructed in 2002 which includes both
enclosed and outdoor areas with a pool and swim up bar. The roof has some pin hole leaks and
there are some water strains evident along the ceiling.
> Fuel Dock Building — An approximately 650 sq ft fuel dock building is located at the T- head of C
Dock which houses the fuel dispensing operation. The concrete floor appears to have been
raised approximately 4-6 in above the dock. There is some corrosion apparent along eave end
of the metal roof. There are several rusting nails along the exterior walls.
Environmental & Upland Infrastructure Summary
In addition to the engineering evaluation of the marina structures at Simpson Bay Yacht Club, the
marina was inspected for operations and conditions which present the most common environmental
concerns. The components of these inspections are listed below with a brief summary of out findings,
followed by several recommendations for additional investigation:
> Potable Water — Water is supplied to the marina via the public water system. No significant
deficiencies were noted with the water supply to the marina. NI potable water uses at SBYC
are metered to make sure there are no unaccounted leaks or usage. Water is charged at the
marina at $0.12/gallon.
> Sanitary Wastewater — No vessel pump out is provided at SBYC. Despite limited potential
usage, provision of a waste pump out is always recommended as well as enforcement of a "no
discharge" policy within the marina basin. Sanitary wastewater from the offices and upland
facilities is reportedly discharged to septic systems on the upland. No known problems exist
with the septic systems. The condominium regime at Plaza del Lago maintains the septic
systems. JImbo's Bar/Restaurant has individual septic systems for the facility.
> Stormwater Runoff— Stormwater runoff does not appear to be a significant problem within the
limits of the property. However, it is believed that stormwater runoff from adjacent areas to the
project site contribute sediment and contaminants to the local waters, and thus may impact
water quality and sedimentation in the marina.
> Fueling System — Sol is responsible for providing fuel and owns and maintains the storage
tanks, fuel supply piping, and dispensers. The supply piping and dispensers were replaced in
2003-2004. The dispensers are in good condition and include 2 for diesel (high speed
capability, one on land and one on the fuel dock) and 1 dual-product unit on the fuel dock. The
UST construction material and tank capacity was not verified. Varied sources of documentation
revealed that the diesel tank holds 10,000 gal and the gasoline tank holds 4,360 gal These
should be verified prior to purchase. There appear to be adequate electric and manual shutoff
valves to stop the flow of fuel in an emergency. There are apparently no local regulations that
would require remediation and/or replacement of the USTs; however, the UST release
described above should be further investigated. No soil contamination in the vicinity of the
waste oil storage areas was observed.
> Waste Management — Solid waste receptacles are provided at the foot of the piers. These
receptacles are emptied daily by marina staff. The collected solid wastes are stored in a
dedicated storage area at the east end of the premises and removed periodically by a local
waste hauler. Waste oil storage and general facility maintenance equipment is also located in
this area.
> Sediment, Water, and Soil Quality - During the period September 26.27, 2006 sediment, water,
and soil samples were collected from 4 locations each within the Simpson Bay Marina. The
5
EFTA01119830
analytical results of the sediment, surface water, and soil sampling effort undertaken suggest
the following:
• Sediment Quality - Antimony, arsenic, copper, mercury, silver, and zinc concentrations
were elevated In marina sediments. Silver concentrations are included because of
elevated MDL values. No PAH compounds or PCB arochlors were detected in any of
the sediment samples. TOC concentrations in all of the sediment samples were
elevated. Tri-n-butyltin concentrations exceeded the USEPA lower screening value by
two orders of magnitude in each of the samples.
• Water Quality - Copper and selenium concentrations in surface water samples were
elevated. Copper concentrations in each surface water sample exceeded both the
acute and chronic U.S. EPA water quality aiteria. Selenium concentrations exceeded
the chronic water quality aiteria value but not the acute exposure value. No PAH
compounds were detected in any of the surface water samples. No dissolved phase
BTEX compounds were detected above their respective MDLs in any of the water
samples. Nutrients do not appear to be a significant concern in the marina waters. The
copper source is likely leaching from bottom paints. The selenium source is unknown
but likely from a natural source.
• Soil Quality - Five PAH and one BTEX compound were detected in elevated
concentrations in soil sample SBM-06SS. The reported analytical concentrations and
weathered petroleum hydrocarbon odors noted during collection of soil samples in the
vicinity of the diesel fuel UST indicated that a relPase of unknown quantity has
occurred. Groundwater in the vicinity of the UST has likely been impacted as well. The
extent and geometry of any groundwater contaminant plume that may be present is
unknown.
> Site Electrical System — The main electrical substations are operated by the Government and
were not accessible for observation during our visit. Since these substations are not within the
control of the marina it is assumed that any power upgrades required for the docks or buildings
could be accommodated by the Government.
> Parking — Only 10 parking spaces are located within the SBYC property, adjacent to Jimbo's
restaurant Staff and guest parking is generally first-come, first-sewed and within the available
surface parking lots in the Simpson Bay/Plaza del Lago development.
> Areas of Environmental Concern— During the inspection, a few areas of environmental concern
were identified. ATM recommends the following for environmental compliance:
• Coordinate with Sol regarding additional sampling and remediation, if necessary, of the
fuel product found during ATM's sampling effort.
• A maintenance dredging fund should be established for potential post-tropical storm
dredging in the basin and in particular, the entrance channel area that may occur. A
regional dredged materials management approach should be considered for all
facilities within Simpson Bay.
• Additional fire suppression pump/foam carts should be considered to supplement the
extinguishers that are placed around the docks.
6
EFTA01119831
PRELIMINARY PROBABLE REPLACEMENT COST ESTIMATE
SIMPSON BAY YACHTCLUB
L, z.r.r ,
ISub-Total:
Item _ I Ouipaiy Unit
FA
IAA*
SSC° :X5
Ss Cost A
1/4,5;00 —1
IWO 000
Depewlent uponrmittewr factors
Nis I Orgy Unit MAt Mons Solt 6191•60assirsan
Fmk) Docks 7 529 SF $150 $,SION main we r Aap and /r2ers
Llama PoveirVilater • PHNSZIIS IS EA $35 COD $56C 000 3- 6 1-ensse sappy to 480v at ;p.c.< sips
Fire Sumas: on • Carers 3 FA OW ' 52550 I Spaced al -15, per WPA
'Subtotal: 51,691 BOO
--anillt WI W alt Nes Cod '-S Ott NollatANIstsra*
Fae0 Coca, 142S6 SF $120 $171Q,90 man awirorap_and nngirs
Manna Power/Waler • Pedestals 96 EA $7,600 B59§22)._ TwicaN 1201206V
Fro SwP/144/05 -COMM 6 EA $850 $6,600 Spaced M-150 per "PA
Manna Sower Purnpoul - Fuel Oot* I EA $70,000 $70000 dedW9010I0Pal WOG Intleort
Fuel Deanna • Dearmacan• I EA $400,000 $400000 Susd css land and fool dock (SO WePowailei)
Sub•Totel. $2.173,710
- agile ;.1 - CYNOS. •-410—: r.lthetr-n. IMmieriale
?Slow/Manna 06/14 * &Wino 1,506 SF $100 IMI gm if from pins
Gs* Hosts 960 SF $100 $96000 if Mr. On
FM Dock ESION9 145 SF $/5 $10875 fair** sans
ssuneruno $066 900 SF $65 $19 500 datumptsila
3mbar Su and Pool VC* SF $n $12 7.5% MIMS Sint
frdp-Tatit SOWS
$6.490,115
Orria0PICY 15% 3870.621
TOTAL ESTIMATED REPLACEMENT COSTS: $6,290,656
1. Tin suns* h ccricscual in napes and not mune* ocwstn/c5cr, Odd
2. Ripsnot casts Clo ec'4e coats d straeline staNisma' tt barn emcawital
& Main taii.ind SutalaineS titaded. NJa We under/ Gowerweet treat
7
EFTA01119832
DRAFT ESTIMATE OF PROBABLE REPAIR COSTS
SIMPSON BAY YACHT CLUB
Item I chouillitY I Unit ',unit I Item CoM I NoinfAsisurnptIons
Fa00 Docks
Man Walkways 9110 SF $20 $182,200
Finger Docks 1,220 SF $20 224,400
Concrete Surface 10.300 SF $5 $51,500
Utilities - Rep* 1 LUMP 215.000 $18000 Provided by Erik Engineerlivo
TOW Immediate Costs $213.100
Item I Quanitfty Unit Mink I Item Ccfl I Nounasinemokins
Fan Docks
Utltes • Repair/Maintenance I I LUMP $350,0001 $350,000 I Plovided by Eon Engineering
UplandPaean
Condlmlnum Office Building:
Lex Repairs 1.508 SF $5 $7,530
Gate House Buildings:
Repot Roof 980 SF $8 27,880
Repair Floor 480 SF $2 2980
Repair Concrete Weas 960 SF $5 $4,800
Repay Window ExterlOr Trice 10 LF $3 $30
Jirribo's Bar 8 Restaurant
Repair Roof 1.700 SF $0 210,200
Fuel Dock Building:
Repair Root 145 SF $5 21,160
Replace Hardware 145 SF $5 $725
Total Year 1-5 Costs 3383.00
TOTAL: $854,185
1. Estimated coals are based upon limited informal:ca. fiefinernimts end eildelens should be ant:crated as additional Infeanabon becomes
avaliabie.
2. AbOve OMIMIllett we kr Informational purposes rely and should net be teed for Metingor consbuclion ourpeass.
I. SF estimates Include covered and open (deck) melons of sauctures
EFTA01119833
APPLIED TECHNOLOGY & MA AGEMEN, INC.
Marina Due Diligence Assessment
Virgin Gorda Yacht Harbor
Virgin Gorda, British Virgin Islands
DUE DILIGENCE SUMMARY
Prepared For
Island Global Yachting
Ft Lauderdale, Florida
NOVEMBER 14, 2006
EFTA01119834
DUE DILIGENCE SUMMARY
A marina assessment was conducted by Applied Technology & Management, Inc. for Island Global
Yachting to assist with the review of the facilities at Virgin Gorda Yacht Harbor, Virgin Gorda, British
Virgin Islands. The review concentrated specifically on the items of Condition Assessment of existing
physical facilities and environmental issues. The major features on this site include the leased shops,
restaurant, and grocery store, boat storage and repair facility, marina office and chandlery, fixed docks,
basin perimeter (bulkhead), restrooms, and fuel storage facility.
Marina Engineering Summary
This marina was constructed in the 1970's and is in generally good condition, save for the concrete
bulkhead that surrounds the basin. The bulkhead remains from the original marina development and is
In very poor, failing condition. The marina piers were replaced In the mid 1990's and are in good
condition. These piers utilize precast concrete elements from PresTCon out of Trinidad, the same
component supplier as on the new Yacht Haven Grande marina.
The marina includes three main dock trees, a single marina pier for larger vessels, and side-tie mooring
along the perimeter. It is noted that the side-tie slips along the perimeter are used mainly by local
fisherman and supply boat operators. No utilities exist for these slips. Main dock trees and the large
vessel pier provide standard marina power and water service via utility pedestals which are in fair
condition. Fuel is available at the marina. A grocery, restaurant, and conglomeration of small retail
stores exists on the property and nicely compliments marina activity and operations.
In addition to the marina wetslips, a large vessel service yard is located on an upland portion of the site
adjacent to the marina. This yard has capacity to store some -300 vessels and is widely recognized in
the region for high quality service offerings. On the opposite side of the marina basin from the service
yard is a large field which is used by locals for outdoor recreation. The upland facility at the manna is
noted as the center of activity for the entire community.
Expansion and redevelopment opportunities at this site are many due to the large upland space
available. This may include the development of additional upland structures and/or an expansion of the
marina basin to augment slip offerings.
Specific areas of required maintenance include:
➢ Immediate replacement of -2,220 linear feet of concrete bulkhead.
➢ In order to maximize the number of useful slips in the marina, construction of marina utilities
along the perimeter of the basin should be considered.
➢ Repair/replacement of marina dropwell which has significant rust on steel bulkhead and
significant concrete spalling and cracking of travel pad/cap
➢ Consider addition of marine sewage pumpout
Costs for this improvement are estimated to be approximately $1,500/linear foot of bulkhead and
approximately $7,000/slip for construction of perimeter marina utilities (-17 slips). This yields a total
cost of $3.33MM for bulkhead repair (assuming a coated steel sheet pile bulkhead driven in front of
existing wall & new concrete cap) which is required immediately and $119,000 for utility improvements
to increase the number of useful slips in the basin (utility improvements suggested, but not required).
Costs to improve the dropwell structure may range from $10,000 for concrete repair and monitoring to
$500,000 for replacement of bulkhead and piers. These costs may be absorbed into redevelopment
plans that shift the marina yard to the opposite side of the basin and call for the existing dropwelVyard to
1
EFTA01119835
be convened to an alternate upland use. A summary of these probable costs are listed on the attached
spreadsheet.
Installation of a marine sewage pumpout may cost on the order of $20,000.
Maintenance dredging does not appear to be an immediate need.
Environmental & Upland Infrastructure Summary
In addition to the engineering evaluation of the marina structures, ATM also analyzed the
environmental condition of the marina and surrounding property, associated infrastructure, and
structures on the property. Each of these components is listed below with a brief summary of our
findings, followed by several reuxnmendations for additional investigation:
➢ Potable Water — Currently, potable water is provided to VGYH via a 3' line from Little Dix Bay
Resort. Due to ongoing expansion plans at Little Dix Bay, VGYH will be forced to conned
directly to the municipal water system by March 2007. The piping and water meter are in
place to make this conrivUkni with the 2' diameter water main. Given the size of this water
main and the reported unpredictable pressure and flow of the municipal water, we concur with
Sun Resorts plan to install high service pumps, 20,0000 gallon storage tank, and chlorination
system. Given peak potable water flows of about 12,000 gallons per day in June and July, the
proposed improvements should provide an adequate supply of potable water. The current
water rate is $25/1,0000 gallons and all uses at VGYH are metered.
➢ Sanitary Wastewater — All wastewater generated at Village Cay Marina is routed to the Little
Dix Bay Resort sewer system via central lift station. Similar to the potable water supply, VGYH
must remove this connection by March 2007. There is no municipal sewer system, so an on-
site wastewater treatment plant must be installed. Sun Resorts has a preliminary wastewater
plan in place, but must make a decision soon regarding treatment and disposal options. The
on-site collection system and pump stations appear to be functioning adequately at the time of
the inspection. According to long-term meter readings, about 42% of the potable water enters
the sewer system.
➢ Stormwater Runoff — There are eight stormwater outfalls into the marina basin. However, only
the outfall originating beNnd Buck's Grocery Store appears to contain offsite strimiwater runoff
and is the only one that is problematic. Buck's Grocery Store and the adjacent businesses
have been flooded in the past due overflows from this system. The onsite drainage area has
been regarded to help prevent this problem, but enlarging replacing the existing 10- line with a
larger pipe will be necessary. There is no sewer system in the surrounding area, so it is likely
that offsite stormwater runoff discharging to the manna basin is contaminated to some extent.
Routing the offsite stormwater runoff out of the basin should be explored.
➢ Fueling System — The fueling fadkty consists of two above ground storage tanks - 8,000 gallon
diesel and 2,000 gallon gasoline. There are no ground water monitoring wells at the tank farm.
The Sol Group (formerly Shell) provides the fuel and is responsible for maintenance of the
fueling system and two gas dispenser and two diesel dispensers. Currently, the tanks are fed
from Little Dix Bay, but when the fuel tanks are moved to the other side of the marina to make
way for the Investment Club development, they will be fed directly from Sol's fuel depot. The
existing fuel lines will be replaced during this move. The existing lines are not that old but
reportedly replaced older lines that were leaking. No evidence of above ground leaks were
observed during the inspection, but additional investigation into the formerly leaking lines may
be warranted.
➢ Waste Management — Two roll off dumpsters are provided for solid waste disposal. There is
no used oil collection facility or other waste collection points, so it is assumed that all wastes
2
EFTA01119836
end up in these two dumpsters. The dumpsters are emptied at a municipal dump on Virgin
Gorda.
➢ Water and Sediment Quality — The configuration of the marina basin and average tide range in
the area precludes very good flushing. Rain events can result in turbid water from offsite
stormwater runoff entering the basin. However, the water quality in the marina basin should be
acceptable from an aesthetic standpoint at most times. Water quality and sediment samples
were collected during a period of fairly dry weather during this due diligence effort. Results
quantifying the water and sediment quality in the basin will be reported under separate cover
when received.
➢ Structural Assessment — The upland facilities consist of the following:
• A single story grocery store
• A single story retail space
• A two story fuel dock, marina reception building
• A dive shop
• The single story Chandlery (ship's store)
• A maintenance shop
• Two retail buildings (under construction)
The grocery store is a pre-engineered metal building. The exposed perimeter of the roof is in
very poor condition and must be repaired. The electrical system within the building is in poor
condition and should be replaced. The facility is "dated" and based on its overall condition
should be replaced within 5 years.
The retail eparp consists of five apparent load bearing masonry, buildings which enclose an
open courtyard. The interior canopy and roof overhangs of the buildings are in poor condition
and need to be repaired and replaced. The storm drainage system including the above
ground and above ground piping is severely undersized and the site drainage is poor. The
facility is "dated" and based on its overall condition should be replaced in approximately 5
years. The fuel docW marina reception building, is a wood framed structure and in good
condition with the exception of the wood deck and stairway which is in poor condition and
should be replaced. The Chandlery appears to be in good condition and the Maintenance
Shop is in fair condition.
➢ Site Electrical System — During the inspection, ATM conducted a cursory review of the
electrical system at this site. Currently, all electrical power is routed through the Little Dix Bay
Resort transmissions system. VGYH will have to be off of this system by March 2007 and
connected directly with BVI Electric. The new transformer for this feed has been purchased by
Sun Resorts and is now in place. The transfer over to BVI Electric should occur within the next
several months. Much of the wiring and switch gear have been replaced, but there are several
areas needing improvement and abandoned equipment that must be removed that are
described in more detail in this repal. A thorough detailed inspection of the electrical system
is warranted. Backing up this system is a 500 kW 3-phase diesel generator in new condition
that can handle the current electrical loads at VGYH. This generator is fed by a new dual-
walled 1,000 gallon steel storage tank.
➢ Boat Storage Yard — This 13 acre area has a reported capacity of 280 boats and is served by
a 70 tone Travel Lift. The boat storage yard is scheduled to be moved to the empty field on
the east side of the property to accommodate construction of a village center by the
Investment Club. The new 11 acre site is reported to be able to handle the same number of
boats. This move will require a facility for the Travel Lift. Sun Resorts also indicated that they
are considering a 150 ton Travel Lift to serve larger boats at the new storage yard area.
Metered water and electricity are provided to the existing yard and all work, other than hull
scraping, is accomplished by independent contractors under the direction of the boat yard
manager. The contractors are responsible properly disposing of their wastes. At the time of
3
EFTA01119837
the inspection, the boat storage area was very dean with no evidence of significant spills of oil
or other materials.
➢ Village Center Construction - The Investment Club has begun construction of a village center
at the existing boat yard area. Sun Resorts indicated that utilities serving this development will
be independent of the marina. Little additional information on this development was made
available at the time of the inspection.
➢ Areas of Environmental Concern — During the inspection, several areas of environmental
concern were noted. There is a potentially PCB containing transformer located adjacent to the
restaurant that is slated to be abandoned in place when the new electrical connection is made.
This transformer should either be drained of oil or removed from the site. At the Travel Lift,
there is an area where boat hulls are pressure washed and scraped. This area drains to a
sump that is pumped into the ocean. The results of soil sampling in this area will provided
under separate cover. Best management practices to contain paint chips and other
contaminants from hull maintenance activities should be considered. In addition, the potential
for contaminated soils from leaking fuel Ines (that have been replaced) should be investigated
as discussed above. This inspection did not include a lead-based paint or asbestos survey.
While no obvious areas of lead-based paint or asbestos were observed, the age of the facility
warrants additional investigation to verify their presence or absence.
ATM recommends the following tasks be undertaken. Probable costs for implementation are attached.
➢ Verify transfer of water, electric, and wastewater utilities from Little Dix Bay Resort. Prior to
dosing. Projected costs are attached should these tasks be undertaken by IGY.
➢ Conduct a detailed inspection of the electrical system to further delineate required
improvements.
➢ Verify that the Investment Club development will have separate utilities.
➢ Conduct lead-based paint and asbestos survey.
➢ Institute marina best management practices in the area where boat hull maintenance occurs.
➢ Further investigate soils along the area where the old fuel lines were located to assure that
contamination has not occurred.
➢ Remove or drain oil from potentially PCB containing abandoned electrical transformer.
➢ Repair exposed perimeter of the roof in grocery store and replace electrical system within the
building. The facility is "dated" and based on its overall condition should be replaced within 5
years.
➢ The interior canopy and roof overhangs of the retail buildings need to be repaired and replaced
along with repairing the storm drainage system. The facility is 'dated" and based on its overall
condition should be replaced in approximately 5 years.
➢ Replace the wood deck and stairway at the fuel dock/ marina reception building.
4
EFTA01119838
FINAL ESTIMATE OF PROBABLE COSTS - VIRGIN GORDA YACHT HARBOR UPLAND COMPONENTS
Convanent
lir_
pledFalflIfes
_Ed Gummy . Unlit SAMILCI. Iva Cost IL -e Rates
Bucks Orocory
Replace damaged roof trarraig 7,000 SF $26 $182.000
Replace Sent panels 8 Wes 4 EA 16.600 326.000
Releace Roof Otatnage and
500 LF $35 117.500
Emergency 5F09901
Retail Space:
Repair Cancoy(Cols and Roof I 1.003 SF 115 $48.003
Replace rod (Back right came 2.000 SF $1 $11.030
Elnwtateledctleuklew al Ward 1
LS 516.000 116.000
SDme
Fuel ock:
Replace stars:dee 500 SF 138 117,000
Overall:
bums Sammy Sower Sweat I LS 1110.000 $180,000 Nodded only II nmommisM0W Sul
Intel Potable Water Trail Sy& I LS $40.000 $40,000 Needed Calf if nc4canpielecl by Sun
Mac Env Inveabgsbona I LS 145,000 145.000
Electical Insoacica 8 Mac I LS $35,000 $35.000
Total Iffenadiate Costa $423.01/4 _ ,
10 5COSTS
STS
TIARA
IIIIIIW-'"="11011111111 Efl1:21fl
Bucks Grocery:
RepGCS soffit 4.030 SF $13 $52.000
Replan Peeked Wawa; 1.000 SF $18 $11000
Papaw Maenad Fascia 210 LF 635 $1.750
Rep ace 09 gnat Respons7) 10.000 SF $13 $130.030
Retail Spat
Rapine Og. In Lae Otc (Tatiled 1200 sF $13 516.600
Roa90117)
ROOM *cm dralagi (above 146.000
and below grad') and regroda I LS $45.000
Candi POW, woblates I LS $16 116
Rice Interior crowbar* 300 LF $193 145.000
Fuel Dock:
Nebo etre Wat 1 LS $3.600 13400
Wirt Facile/1
Repair Root 1500 SF $16 $24,000
Y at 1 - 5 Coils $33&568
01011700010 Clapently I Unll I MUNI • lists Coat i Notes
Upland FAcaMos
Regan Geary Itt:i long 10,000 SF $150 ST 500 000 Sm. Only In feu ti 1-5 year moans
Replace Reim Buidono• 15000 SF 1150 $2.250000 Shea ON. In laud 1-6 year tapers
Teat 5. Coate 13,750.000
TOTAL 0.5 YEARS : $962,666
1. CEstimated coati ant eased eon ntOnmatiOn Refinenlenla and abaticns snsc 3 he antleipatad le aciditionsi infonnabco
es wadable
2. Above eaornates ire Ice ireommaronal papaws only and should not be twol for tithltrog or constructicm purposes.
Cods wore nactand apmernately 20D% 10 account ice constructlat costs in the BT1
EFTA01119839
Virgin Gorda Yacht Harbour
Estimate of Deferred Maintenance/Replacement Costs Nov-06
Marina Components Units Cost/Unit Item Cost Year
STRUCTURES & PUB a I NTITIES
Bulkhead* 2,220 LE 1,500 $3,330,000 0-5
Dropwell Repair" 1 LS $10,000 $10,000 0-5
Sub Total $3,340,000
Electrical service, including pedestals 17 slip $7,000 $119,000 0-5
Plumbing,including water, fire 17 slip $1,850 $31,450 0-5
Communications at slips 17 slip $500 $8,500 0-5
Fire System Repair/Maintenance 1 LS $5,000 $5,000 0-5
Marine Sewage Pumpout 1 LS $20,000 $20,000 N/A
Sub-Total $183,950
OSTS
Engineering Design, Project Manajement 10% % CAP $3,523,950 $352,395 0-5
Development Fees/Permits 2% % CAP $3,523,950 $70,479 0-5
SUBTOTAL $422,874
$3,946,824
*Assume bulkhead replacement. Alternative may be to install revetment in front of existing bulkhead
and timber deck/walkway above. End costs likely less with revetment/walkway option.
RevetrnenVwalkway subject to spatial considerations in marina basin and on upland.
"Immediate repairs required for existing dropwell site. If dropwell is relocated to opposite side of
basin, installation cost will be substantiall higher, in the range of up to $500,000.
If dropwell is kept in existing location, additional repairs will be required within the next 10 years
including replacement of sheetpile and cap. Estimated cost for this —$300,000 (150LP$2,000/LF).
'Includes minor repairs and maintenance only. If major piping repairs are required, costs may be
much higher
EFTA01119840
APPLIED TECHNOLOGY 8. M AGEMENT. INC.
Marina Due Diligence Assessment
Village Cay Marina
Road Town, British Virgin Islands
DUE DILIGENCE SUMMARY
Prepared For
Island Global Yachting
Ft. Lauderdale, Florida
NOVEMBER 14, 2006
EFTA01119841
DUE DILIGENCE SUMMARY
A marina assessment was conducted by Applied Technology & Management, Inc. for Island Global
Yachting to assist with the review of the facilities at Village Cay Marina, Road Town, British Virgin
Islands. The review concentrated specifically on the items of Condition Assessment of existing physical
facilities and environmental Issues. The major features on this site include the hotel, restaurant, two
associated condominiums, fixed docks, basin perimeter (bulkhead), administration offices and
restrooms, and fuel storage facility.
Marina Engineering Summary
ATM conducted an engineering evaluation of the marina structures and utilities. The following highlight
the findings of this effort.
➢ Navigable Depths and Sedimentation Potential — Depths in the marina basin range from 2-ft to
28-ft. and are generally adequate for marina operations and berthing. ATM was provided a
detailed depth survey from Mr. Paul Carrell, the Marina Manager. Depths were checked and
provided to Mr. Carrell by Commercial Dive Services, an on-site diving company. This survey
is presented in the Appendix to this report.
ATM also interviewed marina patrons with regard to marina depths and navigability within the
marina basin. Owners of the Dreamaker, a 49-ft. sailboat moored on Dock A, indicated
generally adequate mooring depths In the marina basin for their vessel. However, a -7.5-ft.
high spot in the entrance channel has proved difficult to traverse at low tide conditions. Marina
patrons since 1994, the Owners of Dreamaker do not recall a specific dredging event between
that time and the present. General observation around the storrnwater outfalls entering the
basin did not indicate any specific shoaling or sediment build up, but this should be
investigated further and monitored.
➢ Shoreline Stabilization — The visible shoreline around the marina basin is naturally vegetated
with no mechanical stabilization observed. The area beneath the restaurant deck was not
observable from land or via kayak. ATM did not investigate the area on the eastern shore of
the marina. There is some build-up of sediment along the south shoreline of the marina fadkty
with specific shoaling/low water depths observed adjacent to the marina office. This area is
currently used for dinghy/kayak/small boat mooring and affects —1 permanent boat slip.
➢ Marina Infrastructure Assessment and Structural Deficiencies — ATM reviewed Piers A-C for
general structural condition and deficiencies. This was done via visual observation from the
deck and via kayak Pier C was reported in the worst physical condition and Pier A in the best,
due to shielding from wave activity from the east The Piers are constructed of concrete and
were designed/built using a steel piling with reinforced concrete caps and reinforced concrete
deck components. Utility chaseways appear to have been cast into the deck components.
While Pier C exhibited definitive, easily observable deterioration of the concrete and reinforcing
bar in decking components, all Piers exhibited similar deterioration upon observation from the
water level via kayak. Concrete spatting, rusting, broken, and disintegrated rebar are typical
throughout main walkway and finger decks in the marina. Topside deck cracking was
observed in several locations throughout the marina also. Though mostly minor, some areas
exhibited signs of significant cracks and stress on the concrete deck. Additionally, some pile
cap deterioration was noted on all three docks. This included rust spots, concrete cracks, and
spelling,
EFTA01119842
ATM understands that this facility was constructed in 1974. The estimated useful life of a
concrete structure in a marine environment is -30 years. As such and as evidenced by the
significant deterioration of all the concrete piers at Village Cay, near-term complete pier
replacement is indicated.
> Marina Utilities Overview — The marina offers three phase and single phase shore power in a
variety of configurations. These offerings are generally well-distributed throughout the marina.
However, shore power pedestals are dated and have been reported to be problematic by
marina patrons (limited plug offerings at each pedestal/decreased flexibility for power at
specific slips, plug collars are reported not to "fir into pedestal housings, and shorts/minor fires
have also been reports).
There is no marina pump out available and as such this promotes dumping in the marina
basin. However, when evaluated against the stormwater/sewer outfalls present in the basin,
this does not present a significant water quality issue. Potable water is provided at the
pedestals. Diesel is available at the facility on the T-Head of Pier A. The dispensers are older,
but appear adequate.
In general, with the need to replace the piers also is a need to replace the dated utilities at the
marina facility.
> Layout and Potential Expansion — The marina layout and fairways are generally adequate for
marina operations. Some catamarans require wider berths and currently occupy two slips.
Access is also generally adequate with some shoaling reported in the entrance channel, which
affects some larger sailboats (which make up a majority of vessels in this and other area
facilities).
It is noted that with the needed pier reconstruction comes and opportunity for reconfiguration of
the marina basin. Though the facility is generally adequate for current demand,
accommodation for some larger slips is indicated to provide berthing for larger yachts and
wider sailboats (catamarans). Expansion opportunities to the west should be investigated
closely in terns of basin limits/submerged lands boundaries. Also, ATM understands that the
slips along the eastern portion of the facility have been leased to an outside entity. Inclusion of
these slips in a basin redevelopment could also provide additional layout options and flexibility.
> Recommendations and Deferred Maintenance Cost Estimate — As indicated previously the
Village Cay Marina is 32 years old. Though some maintenance has occurred with respect to
marina utilities, the marina piers have reached the end of their useful life and are in need of full
replacement In doing so, replacement of the dated utilities is also indicated. A general cost
estimate for the replacement of the marina is attached. This generally represents in-kind
replacement (with appropriate updates, inclusion of pumpout, etc.) and does not include
reconfiguration or expansion.
Environmental & Upland Infrastructure Summary
In addition to the engineering evaluation of the marina strictures, ATM also analyzed the
environmental condition of the marina and strrounding piuperty, associated infrastructure, and
structures on the property. Each of these components is listed below with a brief summary of our
findings, followed by several recommendations for additional investigation:
➢ Potable Water - Water is supplied to the marina via roof catchments with supplemental water
from the public reverse osmosis water system. Potable water is stored on site in a 30,000
gallon cistern and is filtered and distributed throughout Village Cay via PVC piping served by
two 5 HP service pumps. This arrangement is necessary due to extreme pressure changes in
the public water supply due to cruise ship demands. A Dock, however, is fed directly from the
public water system. Typical daily water usage at Village Cay approaches 7,000 gpd and the
2
EFTA01119843
rate for water from the public system is reported to be $30/1,000 gallons. All potable water
uses at Village Cay are metered to make sure there are no unaccounted leaks or uses. The
water system appears adequate to meet the marina's water demands. ATM does recommend
that a chlorinator be installed to assure that the cistern water is maintained in a sanitary
condition.
➢ Sanitary Wastewater — All wastewater generated al Village Cay Marina is routed to the public
sewer system via PVC gravity mains. Grease traps are utilized in the restaurant areas, but
need to be better maintained. There are no sewage pump stations maintained on the property
and no marina pump out facility is provided for the boaters. Treated wastewater from the
public sewer system discharges well to the west of the marina basin and likely does not have
much impact on water quality, but the inadequate collection system results in raw sewage
discharges in the vicinity of the marina basin, especially after a storm event. Several marina
users reported that the odor of raw sewage can be strong enough at times to warrant staying
away from the restaurant and marina. Other than routinely cleaning the grease traps, no
onsite improvements are recommended at this time. There is no charge for sewer service at
this time and we recommend that a letter stating this will remain the case be obtained from
Government.
➢ Stormwater Runoff - Stormwater runoff from the Village Cay property, along with much of the
adjacent areas of Road Town, is directly discharged into the marina basin with no treatment.
The onsite stormvrater management system appears to be adequate enough to prevent
localized flooding problems. Storrnwater generated offsite that drains into the marina basin
area is a cause for concern due to its commingling with untreated sewage. These discharges
result in reduced water quality and unsightly conditions in the marina basin during periods of
wet weather. One storrnwater gut to the south of the marina is reported to carry diesel fuel in
the stormwater runoff but this has not been verified.
➢ Fueling System — The fueling facility consists of a single 6,000 gallon above ground storage
tank for diesel fuel. No leaks or soil contamination was noted and the secondary containment
system appears adequate to contain any major spills. Peak fuel sales during the busy season
approach 6,000 gallons per week at a reported sales price of $3.41/gallon. Delta Petroleum is
responsible for providing fuel and owns and maintains the storage tank, fuel meter, piping, and
dispensers. There appear to be adequate electric and manual shutoff valves to stop the flow
of fuel in an emergency. A small of diesel leak fuel was noted in the dispenser cabinet on the
fuel dock This leak should be repaired immediately.
➢ Waste Management — All solid wastes generated at Village Cay Marina are deposited in a roll
off trash compactor located off property in an adjacent parking lot. A waste oil storage tank is
also located in this area.
➢ Water and Sediment Quality — Due to the configuration of the marina and average tide range,
the marina basin does not flush well. Rain events, combined with the inadequate sewage
system in Road Town, result in significant turbidity and contaminated water entering the
marina basin via nearby storrnwater outfalls. The smell of raw sewage is evident at these
times. Water quality and sediment samples were collected during a period of fairly dry weather
during this due diligence effort. The results will be reported under separate cover. Due to
short sample holding times, fecal colifonn levels were not measured in the marina basin.
However, fecal coliform counts in the basin are likely to be elevated after storm events due to
the sewer overflows and stommater runoff as opposed to operations by the marina or boaters
at the facility.
➢ Structural Assessment —The upland facilities consist of the following:
• A three story building (Bldg A) which includes 9 hotel rooms
• A four story building (Bldg. B) which includes 10 hotel rooms
3
EFTA01119844
• The lower level of Buildings A and B included retail shops, a restaurant marina and hotel
services. The area at the ground floor of the buildings is approximately 6000 square feet
• Single story retail and hotel service space over the cistern southeast of the hotel facilities
• A pool and gazebo with a -stand alone grill kitchen
• A two story Dock Masters office
• Two, 2 bedroom, 2 bath, ground floor condominiums
In general, the property is in good condition. The hotel rooms observed have been recently
remodeled, and the exterior of the hotel buildings and dockmastees office recently painted.
The buildings are generally wood frame buildings with exterior load bearing walls.
The major deficiencies include:
• Roof leaks
• Stairs with a very shallow riser creating a tripping hazard
• A deteriorated covered walkway which supports AC condensers
• Typical yearly required maintenance
> Electrical System — During the inspection, ATM conducted a cursory review of the electrical
system at this site. This system needs minor repairs and abandoned electrical equipment and
wired need to be removed. This system should be inspected in greater detail to assure that all
applicable codes are met Sun Resorts personnel indicated that almost all of the wiring at the
facility was replaced within that last seven years to correct distribution problems at the facility.
Due to unreliable power provided by the public power system, a 3-phase diesel generator on
an automatic switch has been installed and is able to power the hotel, restaurant, pool, and
marina office. This equipment is in good condition. Current electric rates are $0.37/kWhr.
➢ Areas of Environmental Concern — During the inspection, no areas were identified as areas of
significant environmental concern warranting further analysis. These findings confirm the
results of the Phase I Environmental Assessment performed by Property Solutions, Inc. in
November 2004. This inspection did not include a lead-based paint or asbestos survey. While
no obvious areas of lead-based paint or asbestos were observed, the age of the facility
warrants additional investigation to verify their presence or absence.
➢ Parking Facilities — Only two parking spaces are located within the Village Cay Marina
property. Staff and guest parking is dependent on an adjacent dirt parking lot not owned or
controlled by Village Cay Marina.
ATM recommends that the following upland infrastructure and environmental related tasks be
undertaken:
> Conduct lead-based paint and asbestos survey.
➢ Determine long-term viability of utilizing the adjacent off-property parking lot for staff parking
and storage of the solid waste compactor.
➢ Require Delta Petroleum to repair minor fuel leak in the diesel fuel dispenser cabinet.
➢ Install chlorination system to maintain chlorine residual in the 30,000 gallon potable water
cistern.
> Obtain concurrence from Govemment that there is no charge for the sanitary sewer flows.
➢ Repair roof leaks, correct shallow riser on stairs, replace deteriorated covered walkway which
supports AC condensers, implement yearly required maintenance, see attached summary
spreadsheet.
Probable costs for these tasks are attached.
4
EFTA01119845
FINAL LS 71144TE of PROBABLE °SSTS LACLE CAT MAMMA UPLAND COMPONENTS
a. Cliameast
MIIMNISeefila
10.6MMIVIUMIt SAAR 1 Metal 1
4
Sé _ L
ty_lanmsacps 250 613 13,250 —
Mend woos ?Yuri. add no I rA SUM MS00
Re* Weft ard ivoi was 1 lf f6000 i6.000
ads 0
/,55 1/40•No0Pistre. 100 SI 120 M000
Rm. Roof Loa I LS AO* SOLO
Cana Tees Huse atklemp I SAMU* WACO
~at
Ftelle01n1.'1'04010 1.0011610•1 1 FA AM SIAM
IIAM• Sew
Age SI•05
Anse aanc prigIn pomp isms I EA ENO An
096kmattges SIM
Csanci 600.0 lad I M MN A100
Geodes:
SAAA 5 1 IA µOOo 46.000
Oa*
Mot MobessIiSlits I EA $25,CO3 OS=
ISMS lam0160 4 lac Repon I NA 110.022 510000
,--AnSISISSIIEM I PA 43,020 Á0o0
TOY Medals Ca& MIMI
00weemal , Chianuty UM MA/ , Ant Cori ,
Voted swarm
Oda A
R•000. VAndenim gab(IA01 S SA MPOO 040.000
Awe lioNlood Fxdfirilio I LS 616000 MAN
Re* plionsOnagral el
I LS SL000 WM
Sly
II•Sentes101•10.•ai WM It M pAce MOM
Rep* 4110X01 I LS MIM pÁ00
AmirlsOlna 0,61 moSININ I LS $10.023 $13000
MY Mom
Roar Mot A Ms 1 LS SIND KM)
Ropes an 26 ammunisay 200 Y sae $6.800
Rapwenewed tolraev 1$60 SI IIII 11002
Agoura izasnAmLas (VA) 6 SA MMI MO,CCO
0•74,. drsoal Salk 210 $5 SIG $3200
lUleten
Rff L."' ..-11 co SS Vs s,0405
S,r1 LIJ• loot 000 r At 1204002
0.0^1Am
Gurel ryntry wAsno I LS WOO M605
soireenoolawl
flop.. nay al• ha IMO a 126 IM000
iool,G•tobo
Raput tr,iiparalť• WO St MO 14200
RilmOP- .p".""" I 13.003
Av«,. w c.,i 20 1 t A 1200
Ran.. utworSal gaiety
. W ham I LS MUM 223,030
DecooranwsIMM
A.p. was •••••••••• 1 LS SUM Ma
ii•peanoadtbedi 260 St Mt MAO
c.,,,k,
RS, Is0* I IA VISAS tit=
Rosa vow 0600 I IA WOO 13.500
SF• begs 20 LF 010 DM
0/Sde Sava t LS $1.600 la KO
0016606 001.0010 *WO IM SI lil II ex
Vs I -• Cans 1311,110
US I MIS 1 MCer I LIaRt :y
(4.4„,/ halm.
R.I.,. •1“... sr.< pari *- I LS 1 336 OM 05020
Yost S. CoO• t55.eM
TOTAL 0.5 YEARS $463.660
at,
EFTA01119846
Village Cay Marina
Estimate of Deferred Maintenance/Replacement Costs Nov-06
Marina Corn • • ants Quaff Units `Cost/Unit Item Cost Year
— a -
Demolition (all docks) 1 LS $50,000 $50,000 0-5
Pier Replacement 18,320 SF $80 $1,465,600 0-5
Sub-Total $1,515,600
UTILITIES
Electrical service, including pedestals' 106 slip $7,000 $742,000 0-5
Plumbing,including water, fire, sewer 106 slip $1,850 $196,100 0-5
Communications at slips 106 slip $500 $53,000 0-5
Fuel System** 1 EA $300,000 $300,000 0-5
Sub-Total $1,291,100
Engineering Design, Project Management 10% % CAP $2.806,700 $280.670 0
Development Fees/Permits 2% % CAP $2,806,700 $56,134 0
SUBTOTAL $336,804
$3,143,504
*Does not provide for megayacht pedestals/power which would be on the order of $25k-$45k/slip
"May be mitigated/eliminated through negotiation with fuel supplier for service contract
EFTA01119847
Marina Due Diligence Assessment
American Yacht Harbor Marina
Red Hook, St Thomas, U.S. Virgin Islands
DRAFT EXECUTIVE SUMMARY
Prepared For
Island Global Yachting
Ft. Lauderdale, Florida
NOVEMBER 15, 2006
EFTA01119848
DRAFT
EXECUTIVE SUMMARY
A marina assessment was conducted by Applied Technology & Management, Inc. for Island Global
Yachting to assist with the review of the facilities at American Yacht Harbor Marina (AM), Red Hook,
St. Thomas, U.S. Virgin Islands. The review concentrated specifically on the condition of the existing
physical facilities and environmental issues. The major features on this site include six multi-story
commercial retail buildings, a marina office building, an abandoned gas station, an over water fuel
building, fixed docks, a fuel storage facility, and a reverse osmosis (RIO) plant.
Marina Engineering Summary
Overall, the marina is in poor condition. Though it appears that regular maintenance has been
conducted with respect to marina utilities, and repair/replacement has occurred following storm events
(Hugo, Marilyn), the majority of the marina docks (with the exception of D Dock) have reached the end
of their 30 year service life.
ATM conducted an engineering evaluation of the marina structures and utilities. The following highlight
the findings of this effort.
➢ Navigable Depths and Sedimentation Potential — Depths in the marina basin range from 2 ft. to
12 ft. and are generally adequate for marina operations and berthing. Depths in the nearshore
slips are generally shallow and suitable for vessels with shallow drafts. Deeper draft vessels
(e.g. sailboats) are generally accommodated in slips at the end of the docks where depths are
greater. AM staff indicated that they have difficulty accommodating the large number of
sailboat transients in the winter due to depth limitations in the marina. The marina was
apparently dredged in 1996. AYH staff indicated they believed the limited sedimentation to be
attributed to a bed load that is pushed in from easterly/northeasterly swells. The only area
where unusual shoaling was identified existed at the entrance to the fairway between D and E
Dccks. Staff indicated this was caused by the prop wash from a particular large vessel which
docks al the T-head on E Dock.
Tide range typically varies from 0.75 ft (neap) to 1.25 ft (spring). ATM was provided with a
detailed depth investigation (c. 2004) from Mr. Chris Petty, General Manager of AM. Depths
were determined by AYH staff using a commercially available depth/fish finder and recorded in
their approximate location relative to fingers, slips, fairways, etc., at each dock. During the
assessment ATM used a handheld depth/fish finder to spot check the 2004 "survey. It should
be noted that actual depths may vary slightly due to equipment limitations (accuracy and
precision) and variations in tidal stage at the time of each investigation.
Based on the depth investigations and anecdotal information obtained to date, ATM believes
that maintenance dredging will be an ongoing, but relatively infrequent requirement at AM.
Additional effort is needed to calculate dredge volumes, research disposal alternatives and
regulatory permitting issues, and coordinate with previous dredging contractors regarding
potential costs.
➢ Shoreline Stabilization — The visible shoreline around the marina basin consists of a riprap
revetment generally covered with a stand of natural, healthy mangroves. No areas of
immediate concern were identified during the assessment
➢ Marina Sbudures Overview - The Marina consists of six fixed docks labeled A through E and
P Dock. There is a fixed math walkway located adjacent the shoreline along the perimeter of
the marina, which each of the six docks connect to. A dingy dock runs approximately 2 feet
EFTA01119849
DRAFT
below along the edge of the main perimeter walkway. ATM reviewed the main walkway
adjacent the shoreline, docks A through E and P Dock for general structural condition and
deficiencies.
The site visit consisted of observation from the fixed piers as well as from a small rowboat
provided by American Yacht Harbor Marina. Due to the large number of boats in the slips,
observation by boat was limited.
The structural system of the main walkway and docks A through E is made up of 2x6 timber
decking over 2x10 timber stringers at approximately 16 inch on center, supported by reinforced
concrete pile caps. The pile caps are supported by square (or round) 10 inch (or 12 inch)
reinforced concrete piles and are located approximately 12 ft on center. P Dock is composed
of timber decking over timber stringers supported by triple 2x10 timber pile caps. The pile caps
are supported by round timber piles.
• Rebuilt in the year 2000, D Dock is by far, in the best condition of all the docks.
Approximately 50 percent of dock hardware is corroded. There is no mid span utility
support and PVC conduit and multiple utility lines are sagging.
• All dock main walkways, except D and P, have a second layer of decking added
directly on top of the first layer. This causes water to be trapped within the first layer of
decking, leading to quicker deterioration of the wood decking underneath. There are
already signs of softening and rotting of the wood.
• Approximately 50 percent of the concrete piles and 25 percent of the concrete pile
caps on docks A, B. C, and E exhibit significant deterioration (spelling, cracking) and
exposed, corroded reinforcement. Between 80 to 100 percent of dock hardware along
all dock walkways is corroded, except for D Dock.
ATM understands that this facility was originally constructed in 1974 and was renovated in
1990. The estimated useful life of a concrete structure in a marine environment is -30 years.
As such and as evidenced by the significant deterioration on the majority of the concrete dock
structures at AM, near-term complete pier replacement is indicated.
> Manna Utilities Overview — The marina offers three phase and single phase shore power in a
variety of configurations. AYH is in the process of upgrading the electrical system in the entire
facility but apparently has run out of cable. As such, no upgrades have been made to A Dock
and only half of B Dock is upgraded.
• Older pedestals on Docks P, A, and B are manufactured by Hubbell and offer either
1-30A + 1*50A or 2"50A receptacles per slip. Cable is run under the dock from shore
but is not connected to the pedestals.
• Upgraded slips on Docks B and C have refurbished utility pedestals from the former
Yacht Haven Marina and offer 2'50A receptacles as well as telephone and cable for
each slip.
• Pedestals on D Dock are manufactured by International Dock Products and offer
2'50A receptacles as well as telephone and cable for each slip.
• With the exception of the L-head on E Dock, no pedestals exist and shore power
consists of 30A receptacles mounted to the timber decking.
2
EFTA01119850
DRAFT
• Pedestals on the T-heads of docks P, B, C and D offer a mix of three phase (120A)
and single phase (50A and 100A) receptacles for larger vessels.
• Interviews with slipholders indicated that shore power is generally very reliable and
AYH maintenance staff is prompt and knowledgeable when maintenance is required.
• Potable water is provided at the slips, but hose bib connections are separate from the
pedestals on all docks except D Dock.
• All shore power and water is separately metered.
• There is currently no marina pump out available, which promotes dumping into the
marina basin. However, when evaluated against the stormwater/sewer outfalls
present in the basin, this does not present a significant water quality issue.
• Diesel and unleaded gasoline are available at the facility on the T-Head of A Dock. An
in dock' portable fuel system allows slipholders to fill up anywhere on A, B, and C
Docks.
• There are no fire extinguishers or stand pipe system on the docks. Portable fire carts
(chemical foam suppression) are located on A Dock (at the Fuel Dock T-Head and at
the shore connection) and C Dock.
In general, with the need to replace the fixed piers there is also a need to replace the outdated
utilities at the marina facility.
➢ Layout and Potential Expansion — The marina layout and fairways are generally adequate for
marina operations; however, the practice of berthing vessels that are longer than their slips
reduces the effective fairway in some locations within the facility. The absence of finger piers
in many locations provides for more flexible berthing opportunities, but fingers should be
provided with all double-loaded slips in any type of replacement effort (see below).
A mooring field is located in Vessup Bay immediately south of AYH. Individual permits are
issued for each mooring by the Department of Planning and natural Resources (DPNR).
Conversations with Tracy Roberts (Springline Architects) and James Casner, Esq. (Stryker,
Duensing, Casner & Dollison) indicated that due to 1) the presence of the mooring field and 2)
the tremendous regulatory challenges associated with expanding the submerged lands
boundary, expansion of the facility would be nearly impossible. It was also noted that
reconfiguration of the docks may require a new permit.
It is noted that with the needed pier reconstruction comes and opportunity for reconfiguration of
the marina basin. Though the facility is generally adequate for current demand, the need to
accommodate larger slips is indicated to provide berthing for larger yachts and wider sailboats
(catamarans). A move towards larger slips/updated slip dimensions and the addition of fingers
will likely result in a net reduction of slips.
➢ Recommendations and Deferred Maintenance Cost Estimate — As indicated previously, AYH
is 32 years old. Though renovated in 1990, the marina docks (with the exception of Dock D)
have reached the end of their service life and are in need of full replacement within the next 5
years. In doing so, replacement of the outdated utilities is also indicated. Preliminary cost
estimates for immediate repair (life-safety) and 0-5 year repair/replacement of the marina is
attached. This generally represents in-kind replacement (with appropriate updates, inclusion of
pumpout, etc.) and does not include reconfiguration or expansion.
3
EFTA01119851
DRAFT
Upland Structural Engineering Summary
The American Yacht Harbor site includes approximately 82,800 square feet of buildings consisting of
six multi-story commercial retail buildings, marina office building, an abandoned gas station and an over
water fuel dcck building. The six commercial retail buildings are referred to as buildings A, B, C, D, E
and F.
Buildings A thru E are all similar in design and construction. They are built with a combination of wood
and/or steel framing and corrugated metal roofing used for roof cover. Covered walkways with metal
railings surround the perimeter of the buildings elevated floor levels. The metal railings surrounding the
perimeter walkway have severely corroded supports and 1/4 inch bolts which appear to be undersized
for adequate safety requirements. Our interview with Dennis Moon from Sun Resorts mentioned that
they had seen a noticeable difference between the railings along the waterfront side of the buildings as
opposed to the street side. They should be replaced in the immediate future due to safety concerns.
The most significant overall structural issue for buildings A through E is water intrusion and the resulting
damages. The roofing was improperly installed with fasteners through the trough of the metal roofing
and no flashing was observed on the exterior walls of the buildings. The structural elements of the
buildings show moderate corrosion at various locations, but it does not appear that significant repairs
are required at this time. However, if the water intrusion is allowed to continue, there will likely be
significant structural repairs required in the near future. In addition to structural damage, the widespread
water intrusion could result in mold growth throughout the buildings. Depending upon the extent of the
mold growth, mold remediation costs could range from negligible to highly significant.
> Building A— The two-story commercial retail-office building is located on the far Northeast side
of the site. Two sets of staircases are facing each other at the main entrance located in the
middle of the building. Some of the main structural issues observed are as follows:
• PSL wood beams extend to support exposed rafters and declfing. They appear to be
water stained and show initial signs of deterioration. They are intended for dry-use
conditions only, unless properly treated.
• Several tenants complained of water leaks and stain damages to their ceilings. One tenant
mentioned their frustration with frequent electrical shortages and light bulb replacement.
• The exterior perimeter beam is detaching from the PSL beams in several areas.
• The metal railings are corroding in several areas, worse along the ocean front side of the
building. The '4 inch bolts appear undersized and could potentially be a safety hazard.
• The steel beams and columns appear to be corroding in several areas.
> Buildings B & C — An open walkway and elevator separate the two buildings. There are three
sets of metal stairs located on both sides of Building B and at the far end (closest to Building
D) of Building C. The first floor of Building C has a connecting walkway over to buildings D and
E. Some of the main structural issues which need to be addressed are as follows:
• Several tenants complained of significant water leakage and damages caused by water
stains on all three floor levels. At the time of our inspection, a certified waterproofing
company was making repairs to the outside of the corrugated metal roof decking and was
applying three coats of valcon sealant on all the exposed fasteners.
• The metal railings surrounding the perimeter walkway have severely corroded supports
and 1/4 inch bolts which appear to be undersized for adequate safety requirements.
4
EFTA01119852
DRAFT
• The metal stairs show evidence of corrosion in several areas along the bottom and at
support connections.
• The exterior wood trim along the perimeter of the buildings is deteriorating and several are
missing.
> Buildings() & E — Buildings D and E are both located on the far West side of the property. There
are three sets of stairs, on each of the far ends of the buildings and one in the middle of the two.
The structural issues observed are as follows:
• The metal railings have undersized bolts and are corroding at their supports.
• Carpet damage was apparent on the second floor of Building E, where evidence of water
intrusion was noted along the interior wall of the building.
> Building F— A two-story commercial building located at the northwest end of the property facing the
road. The roofing is a flat concrete slab which is supported by reinforced concrete columns and
CMU walls, resting on a concrete slab foundation. The following structural concerns were
observed:
• The CMU walls have several large vertical cracks along both the interior and exterior of
the building, possibly settlement related.
• The concrete stairs along the backside of the building are deteriorating and have exposed
rebar which is severely corroded. These will have to be replaced in the immediate future
as they are a safety hazard.
• An extension to the restaurant attached to the backside of the second floor of the building
had several damages areas. The underside of the concrete slab floor has several cracks
and spelled areas. Several of the wooden beam supports have severe impact damage.
• The concrete ceiling is deteriorating and exposed rebar was observed.
A visual Inspection of the building was done November 2002 by a local engineer. The building was
reported to have similar structural damages as described above in addition to others which had
been repaired immediately following the report. The roof was reported to have water ponding and a
leaking air conditioning unit which resulted in water damage to the interior ceilings.
➢ Ground Level Parking Garage_- The majority of the ground level of buildings B & C consists of a
parking garage, with a small portion under Building C used as a storage/maintenance area. The
parking garage entrance is located on the ocean side of the building, adjacent the marina office
building. It is built on a concrete foundation with steel columns surrounding the exterior and 12 Inch
concrete encased steel columns as the interior supports. The ceilings consist of bar joists at 2 ft on
center which span between steel beams. Approximately half of the ground floor ceiling has been
coated with fireproofing and the other half (nearest the waterfront) has no apparent fireproofing and
is covered with suspended acoustical tiles. Some of the main structural issues which need to be
addressed are as follows:
• Several of the bar joists are moderately corroded and some acoustical tiles are missing or
are damaged. There is also evidence of a water leak from the ceiling, damages were
apparent.
• The concrete wall surrounding the garage exterior has several damaged areas due to
impact apparent and some unrelated cracking visible.
➢ Marina Office — The one-story marina office building is located on the ground level and centered
between buildings B and C, closest to the ocean. There is some minor mechanical damage of the
exterior wall surface and some minor corrosion and water stains apparent.
EFTA01119853
DRAFT
➢ Fuel Dock Building- The building is located at the T-head of A Dock and houses the fuel
dispensing operation. The building foundation is composed of concrete pile caps supported by
concrete piles. The roof is corrugated metal. The hardware along the edges of the exterior is
corroding and the piles and pile caps used for the building foundation are severely corroded and
deteriorated. One pile has already been added by extending the concrete pile cap over it. The
repair estimates are included in the estimated repair costs for Dock A.
➢ Abandoned Gas Station — A very small building located on the far Northeast side of the property.
adjacent Building A. The abandoned building has some minor maintenance issues.
Environmental & Upland Infrastructure Summary
In addition to the engineering evaluation of the marina structures at AYH, the marina was inspected for
operations and conditions which present the most common environmental concerns. These areas
include:
1. Petroleum storage & handling - fuels, oils and used oil
2. Maintenance operations
3. Solid waste storage & handling
4. Wastewater conveyance and disposalttreatment
5. Spills and illicit discharges
6. Boating & operations related pollution
It should be noted that for a thorough evaluation of each of these areas, a complete review of all
permits and inspections would be necessary. In many cases, ATM would need to call regulatory
agencies to insure that the permit documents being reviewed were complete and up to date. This level
of effort was not undertaken during the review process. ATM also analyzed the associated marina
Infrastructure on the property. The components of these inspections are listed below with a brief
summary of our findings, followed by several recommendations for additional investigation:
➢ Potable Water — Currently, AYH contracts with TSG Technologies to provide chlorinated
potable water from an on-site reverse osmosis (RO) water treatment plant which draws raw
water from beneath B Dock. TSG is responsible for producing up to 25,000 gpd of potable
quality water that is pumped to a series of cisterns located under Buildings A and B. The
cisterns are in good condition and provide over 100,000 gallons of storage. Water from the
cistern is filtered, chlorinated, and disinfected via UV radiation prior to entering the PVC
distribution system at 60 psi via to 5 HP pumps. An additional cistern is located beneath
Building F and serves only the laundrornat in this building.
Normal water usage is 15,000 - 17,000 gpd, with a maximum usage approaching 21,000 gpd.
M uses are metered with an average rate of $0.14/gallon. Water costs from TSG include a
$5,500 monthly base charge plus $10.31/1,600 gallon minus a power adjustment depending
on the monthly electrical costs. This system is in good condition and operates under a public
water utility permit with the discharge of brine to the marina basin under a TPDES discharge
permit.
➢ Sanitary Wastewater - All wastewater generated at AYH is directed to an onsite lift station and
pumped to the municipal wastewater treatment plant. The duplex lift station has a high level
alarm and has recently been refurbished with new pumps. This system appears to be
functioning adequately. Currently, AYH is not charged for wastewater disposal. AYH staff is
reported to be seeking a letter of concurrence from the Water and Power Authority (WAPA)
that this will remain the case. AYH uses a portable pumpout system to service boats with a
charge per pumpout of $35.
6
EFTA01119854
DRAFT
➢ Stamwater Runoff — NI AYH roof areas are piped to the cisterns to augment the potable water
supply. Runoff from AYH parking areas and roadways are routed to two french drains located
adjacent the marina basin. These french drains are basically gravel filled pits that are designed
to catch stormwater runoff and percolate it into the ground in lieu of storm water running
directly into the marina basin. This system appears to be operating below its capacity and
there is evidence of direct runoff to the marina basin. However, the first flush of stormwater
containing the bulk of the pollutants picked up from the roadways and parking areas is likely
contained on site. This french drain system should be rehabilitated to improve aesthetics and
prevent stormwater discharges from AYH directly to the marina basin. There was no evidence
of flooding problems on the AYH property. Offsite stormwater runoff from the surrounding
properties and roads discharge directly to the marina basin.
➢ Fueling System — The fuel storage and transfer facilities generally present the largest
environmental threat in most marina operations. The following section provides general
discussion regarding the review of this facility.
Summary of capacity, tank type and containment description
Four - 10.000 gal double wall USTs - Permatank construction, 3 diesel, 1 unleaded
Dne - 1,000 gal AST diesel (generator)
I One -200 gallon AST diesel (generator belly tank)
One- 400 gal MT used cd In double vrall tank in secondary containment vault
The fueling facility consists of four underground storage tanks — three 10,000 gallon diesel
tanks and one 10,000 gallon unleaded gasoline tank. These tanks are located in the parking
area at the front of the main building. According to the owner's representatives, these tanks are
Permatank construction, which utilizes a UL-58 steel tank wrapped with a polyethylene stand-
off material and mylar sheeting around the outside of the tank. It is coated with a laminate
mylar sheeting with fiberglass reinforced plastic (FRP) to provide both corrosion resistance and
interstitial capacity. The tanks utilize composite manholes and overspill containers at the fill.
The visible part of the system appeared to be constructed of high quality components, and in
good operational condition.
The tanks are surrounded by a series of ground water monitoring wells. During the site
investigation, ATM collected a groundwater sample for analysis from one of these adjacent
monitoring wells. In addition to the groundwater monitoring wells, the UST system is monitored
by a Veeder-Root TLS-350R Monitoring System. The fully integrated system automatically
collects tank tightness testing results, dispensing data, in-tank inventories and deliveries, and
reconciles total at selected intervals.
Conveyance from the USTs to the pumps is accomplished utilizing double wall flexible piping
designed specifically for use with fuels. Several sump areas were unsecured, and available for
inspection, including the shutoff valves near the USTs, and the quick connect sumps located
along Dock A. Entry boots were utilized where fuel lines penetrated these containment sumps.
Several sumps contained water, estimated to have come from stormwater (leaking cover) or
seawater (leaking boot). As many of the covers were constructed from wood to match the
decking, stormwater intrusion into these sumps would appear the probable source.
Fuel is dispensed by either of the two twin hose Gilbarco dispensers located at the end of
Dock A. Both dispenser units utilize extended hose reels, and appear to be property installed
on polyethylene containment sumps. Several quick connect fittings were located along Docks
7
EFTA01119855
DRAFT
A, B and C for use with the portable pump units. All sumps were dean and appeared in good
condition. The visible part of these systems appeared to be constructed of high quality
components, and all were in good operational condition.
A small generator with a belly tank (— 200 gallon capacity) is located on the roof of Building C.
The generator serves a tenant in Building C, and Is believed to be serviced and fueled by their
contractor. There is no provision for remote fueling. The fuel tank appeared to be structurally
sound, however did not appear to have secondary containment. A leak from this tank would
drain through the roof drains into the cisterns. Consideration should be given to providing this
system with updated remote fill capacity, as well as secondary containment for the tank
system.
➢ Waste Management — Three roil off dumpsters are provided for solid waste disposal. The
monthly cost is $1,100 through a contract with Yes, Inc. A —400 gallon used oil tank Is located
along the western side of the facility, west of Building E. Used oil is collected here and properly
disposed of by an outside licensed contractor. The sump area was generally very clean, and
contained several small (<5 gallon containers) of unknown material. There were no
environmental or operational problems noted with the used oil collection area.
➢ Water and Sediment Quality — The configuration of the marina basin results in good flushing
as evidenced by relatively clear water and fairly abundant fish life around the marina basin.
The local wastewater treatment plant empties into the water to the west of the marina and may
result in elevated fecal coliforrn levels in the water if not functioning properly. Anecdotal
evidenced obtained through Interviews of marina customers indicates that the plant has failed
in the past, but normally operates well. Rain events may result in turbid water from offsite
stomiwater runoff entering the basin. However, the water quality in the marina basin should be
acceptable from an aesthetic standpoint at most times. Water quality and sediment samples
were collected during a period of fairly dry weather during this due diligence effort Results
quantifying the water and sediment quality in the basin will be reported under separate cover
when received.
➢ Site Electrical System — During the inspection, ATM conducted a cursory review of the
electrical system at AYH. Power is provided by WAPA at an average cost of $0.32Anstir
through a series of four 3-phase 500 KVA transformers located at the end of A, B, C, and D
Docks. These transformers serve the entire AYH property with the exception of Building F
which is fed directly from WAPA. The transformer at the end of A Dock is exceeding its rated
capacity and is scheduled by the owner to be replaced. Due to voltage fluctuations at the
transformer at the end of B Dock, this transformer is also scheduled to be replaced.
Most of the wiring and pedestals on the docks have been replaced with the exception of
portions of A and B Docks and all of P Dock. The owner plans to complete the rewiring project
on A and B Docks in the near future. P Dock is leased property however AYH has offered the
owner of P Dock to install the electrical upgrades for free if they will pay for the equipment. To
date, no progress has been made towards upgrading P Dock. The remainder of the electrical
system at AYH appeared to be in reasonable shape and is functioning well. A thorough
detailed inspection of the electrical system is warranted to assure that all equipment and
meters are functioning properly and meet applicable electrical codes. Backing up WAPA is a
Broadcrown 250 kw 3-phase diesel generator in new condition. This generator is wired to
provide power to the marina office, maintenance room, RO water plant, fuel dock, exterior
lights, sewage pump station, and several of the restaurants on site. The generator is fed by a
new dual-walled 1,0O0 gallon steel storage tank.
➢ Parking — Both above and below ground parking is provided at AYH. According to the
property survey provided to ATM, the parking garage below Building B encroaches onto the
public right of way by up to 1.5 feet in places.
a
EFTA01119856
DRAFT
➢ Communications/Television — Telephone service is provided through the local telephone
company, as is Internet service to the building tenants. Television service to the marina is
provided by a Dish Network rack system located in the marina office. Internet service is
provided to the marina via a wireless system operated by Ackley Communications. In
exchange for allowing Acldey to provide wireless services to the marina, they provide a free
DSL line for the marina office.
➢ Areas of Environmental Concern — No material testing was performed as part of this site
investigation, but due to the age of the structures, the presence of asbestos containing
materials (ACM) within the building is expected to be limited or non-existent. No ACM
materials of concern were noted during the site inspections. While most of the transformers
onsite were unlabeled, those that were indicated that the units were PCB free. There were no
overhead transformers onsite, and no evidence of leakage from any of the transformer units.
Due to the age of the facility, the presence of PCBs associated with the transformers is not
expected.
Action Items
ATM recommends the following tasks be undertaken. Probable costs for implementation are attached.
➢ Repair damaged concrete pile caps and piles for A Dock within one year. Consider
reconfiguration opportunities.
➢ Repair or replace damaged structural components for the main walkway and docks A, B, C,
and E within one to five years. Consider reconfiguration opportunities.
➢ Renegotiate lease of P Dock and replace/reconfigure within one to two years. Consider
reconfiguration opportunities.
➢ Upgrade utilities on Docks A, B (as necessary), E and P.
➢ Obtain letter of concurrence from WAPA stating that there are no wastewater disposal fees
associated with pumping domestic wastewater to the municipal wastewater treatment system
➢ Rehabilitate the french drain stormwater collection system.
➢ Resolve the issue pertaining to the incursion of the parking garage beyond the AYH property
line into the public right of way.
➢ Verify that the 500 KVA transformers located at the end of docks A and B have been replaced
by the owner.
➢ Verify when the electrical wiring and pedestal replacement project for docks A and B will be
completed by the owner.
➢ Recommend further inspection of the electrical system to ensue adequacy.
➢ Conduct lead-based paint and asbestos survey.
➢ Remove generator and single-wall fuel tank from the roof of Building C
9
EFTA01119857
DRAFT ESTIMATE OF PROBABLE REPAIR COSTS
AMERICAN YACHT HARBOR
all- km I ateadeled I UM I *AIM I Nen Celt kr-OSINSISWESe
Rod Oodo
Dock A
Raper Cameo Res 4 AM Cm 42 EA $750 $31.500 30% money cenctim
Pwlineler MIMI,/
Repo l.44 Axiom 1 EA $300 $300
Replace Deana Soda Dray Dock ICAO SF $A $$6500
Dock Raper Costs 1111.300
Wandraokties ______ ....._ ...
Sum% A:
Replace Psi. ROM 9 Rote Bans 9232 SF $15 $136500
Replace Rallnat 460 LF $26 511.60)
!Milne II 4,5:
Ream Rodeos 1603 LF $23 $40.003
Salm 1) It 6:
Replace Reeve 540 IF VS $13500
Banc FT.
Replace Woof De* Remind 523 SF $13 $7.40)
Radice Conan Slain 1 LUMP 510.000 $10090
8661$716 MP* Coale IMMO
/thence/0
Assam& &Monne Sudiee $ACCO
Replace ID 500We IlinsIonnes 540.000 4 Sun Resod, has ncl ompla04
Intnebectere Repair Cab Sal
Total Immediate Car* 1404.300
I tlearity I OM I I Dee CaM I NOS - MIMMi
Sired Docks
Dock A:
NPR* Wood Dont% Wears and Ron Jove i Lula> $39,000 139.000 40% Rene
Replace Damped Comm klocrim Alm 21 EA 11.000 $21.033 60% dread
Replace Corroded Dock Hardee% 3.825 SF $2 17.650 96% demled
UteletWeed UMW Pe0eas 12 EA $3,560 142.000
Dee IV
Replace Wood Dadole wain and Am JOS 1 RIM 137,000 $37,000 70% rim!
Ream Canoe* We I& We CM 20 EA 0000 $20.000 15% oodcdeS 4 Mar oposel
Replace Dammed CMCM0 Mom] Piss 19 EA $1.030 $19.0:0 00% deemed
Reim Omded Dock Hardman 3.063 SF 12 $6,126 00% cenae0
LIPT0WNMIAMNAKIntals It FA 13,603 1/24.03)
Dock C:
Repo Mod DRIMa Maim ere Rim Joe 1 LUMP MAT 85.M0 70% dammed
Replace Concrete Alos 6 PP. Da ID EA $1.003 $161103 20% fl ed A Me mcm2
Remo Concrete Roma Res 13 EA 11.003 $13.000 50% dammed
Replace Caroded Dock /804me 2.331 SF $2 14.662 90% corroded
Deck E:
Replace Wood 04002. Reim and Alm Mb 1 LIMP fiasco 516.000 75% dioneted
Repine Comet Ries II Re Cm 14 EA 51.003 514.000 25% corroded 4 Me owed
Replace Donde] Ora Herds% 1,661 SF $2 13222 90% COMM
Replan Wood Hose Wider 1 EA $200 $200 damped
UPDMV461 UM ROOMS 1 WIS 113.$00 $13,500
PeeleeatteMtkeeer
Replace Woo! Distal RR .kisls 1 LUMP MOM $62.000 90% dimmed
Replace Coale PlIm & Pie CM 70 EA $1,000 MAO 25% ccaccied li Mr Recited
RSA* ConOtel Pock MAMA, 6.516 SF $2 $13036
0001 P
Replete FernJose AM UR PR Cage 1 LUMP MO 19(10 $G% damned
Rome Damaged Tarter Pate 30 EA 1400 124ECO 90% demos,
Reelect Cctoded Dock lisrdest 1.590 SF $2 $3.00) 75% eroded
nedestele 14 EA $3500 /MECO
Dock , F.egair
host 1$71,476
2.4enteekancee ...Inada/%2
vooDeetco 1 LS TED 79D so:WM in...0TM. _.
Dtdo nd and Depose 100 CT TEO TOO mime mvesepton
laaintenseca Ondienp Cab TED
6,F }M1ln
Dane F metes
Sunding_A:
Aspect Floe. Exeter Dim old Sews 1 NAP $70.090 1 70.000
Repot RIM Beam IS Colunve 290 SF $500
Ryan. Intro' Wet 460 IF $4030
Relkary St C:
Reek Cam% weak EMS:, TM and Stoke LIMP 153.0(0 $53,033
ReMeoe/Repar Deem S Roof LAW $345.000 5345.orpo
RepleCe LA10 Rases 10 EA $500 15,030
Odober 2006
EFTA01119858
Seeding D 6 E:
Raj:race Rod 1360 SF 31 827020
Raplace Cartel 1,061 SF $1a $20.034
Replace Steel 1 LUMP $21100) $20.030
Build F:
Deese Ccocnsle Vest Floor 4 CSC 1 LISIP WAD $96,000
Replace ~Wm 1 EA 62.003 72,000
Fuel Doci. Bulkier
Replace Roof 303 SF $3.003
Replace ExlielOr Tem VD SF C $3:000
Replace RICCIVOT 302 SF $2 3700
aulklail Race Costs wane
InaelevOlr•
Rahablital• Sawn Drains $30D0)
Drove redarrovated Watt , 15 000
Intratruclaire Repair Can 175,006
_ ..
Total Year 1-5 Costs 61264736
rten i army i urn I WM I Noe Cost I Ilan
Foal Dan
Dock D:
ROAM /I • 1,872 SF 62 14.000
Dealt P.
Repiace twang 1.000 SF 66 SLIM
Total Year 5+ Costs MAN
TOTAL 0-5 YEARS COSTS: $1,679,038
1. Estended was an based We rase at Renew* and stsitorts SI101/417 be antopare as laddle011i Meese Mont swats
2 non awns meter ofontaionti Noma car aro steed nova wed for bdarg or cocataucton paean
3 SF minutes ands covered and ape gack) aortas clotwant
Otattot 2006