From: Ann Rodriquez
To: Leighton Allenby
Cc: Jeffrey Epstein <jeevacation@gmail.com>, NYC - Richard Kahn
Subject: Re: Big N update
Date: Tue, 18 Aug 2015 10:45:47 +0000
Inline-Images: imagel.JPG; image2JPG; image3.JPG; image4.JPG; image5.JPG; image6.JPG;
image7.JPG; image8.JPG; image9.JPG; image10.JPG; imagell.JPG; imagel2.JPG;
imagel 3.JPG; image14.JPG; image15.JPG; image16.JPG; imagel 7.JPG
imagel.JPG
image2.JPG
image3.JPG
image4.JPG
image5.JPG
image6.JPG
image7.JPG
image8.JPG
image9.JPG
image10.JPG
image 1 LJPG
image12.JPG
imagel3.JPG
imagel4.JPG
17:7:,54
EFTA01191696
2,image16.JPG
2,image17.JPG
Ann R.
On Aug 17, 2015, at 10:27 PM, Leighton Allenby < wrote:
Boscoe, Anna and I meet with Gene Jr today to review progress of Big N.
I. Boscoe will start tomorrow to finish small items so he has completed before he goes away from 9/1 to
9/13 for some minor surgery. (approx 35 hrs to complete)
I. fill engines with oil and coolant
2. install new clamps and hoses where needed
3. install parts list
2. Hydraulic install completed by tomorrow and then fill system and test
3. Rebuild battery boxes - they built to large, batteries will move around - they agreed with Boscoe
4. They are finishing the plating and side plate repairs/testing the welds and re-welding where needed -
looks great
I. they found 12 more small areas to spot plate - no additional cost
5. Last week in August they will side and bottom sand, prime & paint Big N
6. 1st week in September launch and sea trial and make final adjustment/modifications
7. Returned to us by September 4th - to be confirmed on August 28th
pictures attached
Rich,
As I mentioned to you Boscoe is staying on top of welders for quality of welds. He noticed and pointed out a
few welds that were not correct and Gene will correct. He is looking out for Mr. Epstein. They also want to
update radar and GPS - roscoe is pushing them to find someone to fix. Gene Jr said $10k to update to new
Garmin - We told him to make repairs and fix - no need to replace for what we do with the barge.
Leighton Allenby
Director of Pro erties