From: Jeevacation <jeevacation@gmail.com>
Sent: Saturday, April 18, 2009 11:58 AM
To: curtis R
Subject: Re: Master suite draft budget
Curtis - I've asked twice for =hotos of nursery -please follow through on a more timely =anner
Sent from my iPhone
On Apr 17, 2009, at 5:04 =M, curtis R > =rote:
In the General Conditions -$63,500 - Boscoe, Bruce , Casey =nd Carlos and Arran and any other labor —.
=nbsp;This gets billed back to the construction budget
As well as Demolition $30,000
If we build with our own manpower, which we could, we would save. But it =ould take from other island projects
,of course.
This budget is based on subcontractors for
Rock work
Concrete
Electrical
Milwork
Plumbing.
On this one - We might be able to use Gary for the electric, Brian/Arran =ombo for the plumbing — etc . we
could do our own =oncrete — but ..
Is that what you mean?
On 4/17/09 4:37 PM, "JEE" <jeevacation@gmail.com> =rote:
give me incremental cost.. plese„ =oscoe salary and others is a fixed cost whether or not i build
On Fri, Apr 17, 2009 at 3:50 PM, curtis R > =rote:
Jeffrey,
Please find attached Draft Budget for the Master Suite.
Notes:
1. Demolition will include what is almost a ful gut job.
the entire roof
all the columns
the existing floor in the bedroom section.
EFTA_R1_00099787
EFTA01780920
2. The finishes need to be honed down and represent a large unknown.
3. The cost is around $600 per square foot for a total of 1,372,690
Call to review with Silvina or me for scope adjustment as needed.
Curtis