Sent: Friday, March 18, 2011 7:12 PM
To: jeevacation@gmail.com
Cc:
Subject: Gil update
just
Gentlemen,
The right gear is completed and will=be shipped today. We should receive this by Monday.
The left gear is in the machine shop= they have performed an NDT of the effected area and it appears there is
enough=20 material to remove the corrosion and remain within limits. They will proce=d this weekend with the
machining and check the remaining thickness again on=20 Monday and get engineering involved for approval as well.
There is still=a good chance the corrosion is beyond acceptable limits. I should have an answer=no later that Tuesday on
this gear leg.
Everything else is just about wrappe= up.
If you have any further questions,=please feel free to contact me.
Have a great weekend!
Best Regards
Jet Aviation St. Louis, Inc.
Joe Allen
Gulfstream Customer Support Manager