To: Jeffrey epstein[jeevacation©gmail.com]
From: Gary Kerney
Sent: Tue 8/9/2011 1:27:01 PM
Subject: RE: 5 palms
not yet, need following
to layout slab I need new engineering of the foundation footings and steel supporting the high walls
comfirmation on the door openings size and locations
confirmation on size 16x32
From: Jeffrey epstein [mailtoleevacation@gmail.com]
Sent: Tue 8/9/2011 8:44 AM
To: Gary Kerney
Subject: Re: 5 palms
Have we done anything to site?
Sorry for all the typos .Sent from my iPhonc
On Aug 8, 2011, at 10:07 PM, "Gary Kerney" wrote:
latest plan attached ,the changes inside prompt revisiting the concept
ceiling apply canvas
install big bookcase
any doors on east or west walls?
what is the roof
copy flagpole building?
plaster exterior?
image for doors?transom?
I'm showing all walls to be 12"block,if we thicken the door wall it robs floor area or maks
building bigger(comment?)
I am forwarding this plan to the engineer to do preliminary structual ,won't go far tit floor size is
agreed to.
we are assembling the cabinet in the warehouse
<110808134937-001.pdf>
EFTA_R1_00255522
EFTA01857583