From: Larry Visoski <
Sent: Thursday, April 20, 2017 4:02 PM
To: Je vacation; Rich Kahn
Subject: Nautica update
Attachments: IMG_1201.1PG; Untitled attachment 00238.txt; IMG_1198JPG; Untitled attachment
00241.txt; IMG_1197JPG; Untitled attachment 00244.txt; IMG_1202.1PG; Untitled
attachment 00247.txt; IMG_1203JPG; Untitled attachment 00250.txt
Jeffrey
Raining in Fla„ can't paint today,.
-Interior side panels are primed and ready for High gloss paint,.
-raised side walk Way is ready for paint„ -mid seat with 2" angle is ready for install„ -raised rear bench seat back is ready
to install,.
-metal shop fabricating hand rails
Shop estimate till completion 3 weeks,.
I'll say, 4 weeks,. Ready to ship to LSJ
Thx
Larry
Raised side ledge ready for paint
1
EFTA_R1_01417052
EFTA02391194