From: Ann Rodriquez
Sent: Thursday, January 4, 2018 4:46 PM
To: jeevacation@gmail.com; Rich Kahn
Subject: WAPA Update
Bryan's electric guys confirmed 2 d=ys of Splicing & getting the new Manhole in. If the same crew that work=d today
come back out on Saturday we "might" be able to hav= WAPA on Monday
Ann R.
Begin forwarded messag=:
From: Hugo Hodge «= href="mailto >
=ate: January 4, 2018 at 10:27:27 AM AST
To , Ann Rodriquez
Subject:<=b> LS1
Good morning All,
We have started the wor= on LSJ. From my initial estimate, it will take 2 full days to get the ca=le spliced with
the new manhole in place. Once that takes place tomorrow we=will then test the cable (Hi-Pot test) and then leave the
cable energized f=r at least 24 hours. After that period, we will then go through the steps t= put LSJ back on WAPA's
Grid.
HH</=pan>